Q 30 Slack is related to event not activity... To answer b nhi ho skta And vese bhi critical activity has zero float.... But critical event has minimum slack
Q. 21 answer will be minimum.... Bcz suppose their are 4 paths and their slaks are 2,3,5,7.....then critical path will have slak value 2...it will not zero.,. So most appropriate answer is B
16 mein d hi aayega koi doubt full nahin. Explanation option a,b and c mein koi kaam ya to start hua h ya complete hua hai but in d class is being mean koi kaam ho raha hai, na to start hua hai aur na hi complete.
PERT- each activity kahe question mein to follow beta distribution But poora project kahe PERT ka to fir normal distribution he ans hoga CPM- Normal distribution followed
@@sangeetakushwaha9063 waste management ki subject 5th semester me thi yrr Abhi to McQ base koi content nhi h es subject se related to yrr Nhi to will definitely share with you
free float ki definition h ki amount of time by which activity delayed without affecting Succeeding activity. lekin question m pucha h ki free float can affact? wo aise nahi puch rha ki kispe depand karti h. bro I may be wrong, agar m galat hu to batana muje..
@@harishjorwal2466 NOW CLR 28 _ FREE FLOAT ME SUCCESSOR AFFECT NHI HONA CHAHIYE PRECEDER HO SKTA H 44_ SLACK ME EVENT MINIMUM OR ZERO HONA CHAHIYE NA KI ACTIVITY
Q no 28 me Free float- An activity can be delayed without affecting EST of succeeding activity likhwaya tha..means succeeding activity pe koi affect nhi pdega..so B is the right answer
Sir in lecture 4 video you said that Free float depnds on Succeeding Activity, But in this video Qn no. 28 you said that free float affects Preceding activity....Which one is correct sir ??
free float does not affect succeeding activities means does not depends upon succeeding activities and in question 28 it is asked that free float depends on so it affects or it depends on preceding activities not succeeding activities
You prolly dont care but if you guys are bored like me atm then you can watch pretty much all of the new movies and series on InstaFlixxer. I've been binge watching with my girlfriend for the last couple of weeks :)
And sir aap jo bta rahe ho wo particular activity k liye hota h..... Float < 0....super critical activity Float=0..... Critical activity Float>0.... Sub critical activity Perticular activity critical and path critical.... Both are different..... Detail numerical se ye doubt clear kro
Bhai 30 aur 44 questions same pr Answer Alag Alag q bata rhe ho .. Slack time in pert is minimum for critical event ..slack depends event not activity..
critical activities kai lie 0 hi to btaya hai sir apne q. no 44 ka btao sir???? iske phl bhi ye same qstn hai q no. 30 usme to apne 0 hi correct mana hai to 44 mai glt kyu???
@@engineerpoojajorwal jo idea deta hai woh owner deta hai.... Jo design tyar krta hai woh engg krta hai.... Jo building construction krega according to engg design woh Contract hota hai Ho gya clear 👍
Kya sir aap ne 28 bale question me btaya ki free float Preceding activities pr defend krta h Or phle jb total float btaya bha apne kha ki free flaot succeeding activities pr defend krta h... Ye kya h sir khud hi apni baato se ese confusion peda krte ho or pir hum bi yha bete bete confusion peda kr lete h mind me pir question galat hote h toda dyan se pdaya kro sir hume jo aap pdayege bhi krke aane bale h Esliye plzzz toda espr dyan de
sir, apne pert m beta distribution likhaya hai or cpm mai normal distribution TABLE mai to fir ye qstn no. 41 mai ans galat btaya hai apne ya notes mai ulta likhaya hai sahi kisko manu...??????
PDF- drive.google.com/file/d/1yvRg-Do3ZBEP3vSnLAeEEFntZOOkLeZl/view?usp=drivesdk
5
Please send pdf copy
Q 30
Slack is related to event not activity... To answer b nhi ho skta
And vese bhi critical activity has zero float.... But critical event has minimum slack
Shaandaar content gurudev Gazab ka....1 no. keep it up sir ji god bless u😊
Thank you so much for your support
Bahot achaa lgta he sir apka padhana 🥰🥰🥰
Good contents sir yesa contant to रुपए m bhi nhi milta sir ,,,,,keep it sir 🎉🎂🎂👍👍👍
wahh sir..asan bhasha me pura subject revise hogya... Thank you
Thank you sir amazing video all technical subject thank so much sir
NYC concept sir amazing explanation
Bahut achchha questions content h sir salute 🔥🔥🔥
Question no. 30 ka D shi hona chahiye I think
Question 16:- PERT is event oriented.
Option given is :-D Class is being attended this is an activity so option D is not PERT event
Maan gye bosss....1 no. For Je
Bahut accha padhaya sir Ji
You are best one 👍👍👍👍🙏🙏🙏🙏🙏
Q. 21 answer will be minimum.... Bcz suppose their are 4 paths and their slaks are 2,3,5,7.....then critical path will have slak value 2...it will not zero.,. So most appropriate answer is B
Very nice sir thankyou
Sir Q. 30 and Q44, both are same with same options, but app alg alg answers bolte hai sir..
True
Right....But B is the right .ans
In question 30 answer will be option D becoz in option B its said for critical activities and slack is always for events💯💯
Thanks guruji..... great गुरूजी....
Zero is not always correct.... But minimum is always correct
16 mein d hi aayega koi doubt full nahin.
Explanation option a,b and c mein koi kaam ya to start hua h ya complete hua hai but in d class is being mean koi kaam ho raha hai, na to start hua hai aur na hi complete.
Q41- it should be beta distribution🤔 bcoz its about PERT not CPM
PERT- each activity kahe question mein to follow beta distribution
But poora project kahe PERT ka to fir normal distribution he ans hoga
CPM- Normal distribution followed
Bhut shi pdaate ho sir ❣️❣️❣️
Owner answer aayegaa 👍
As idea n money owner ki hoti hai....
Best teacher for je
Very nice sir ji
Shandar
Sir Q.30 orQ.44 both questions are same but your options is different please explain wright answer of both questions
Both question asked in others exam and IES answers is more appropriate.
Unki jo Answer key thi usme jo Answer the wo Answer batye h.
Samjha gye?
Pr hme concept ke acc to...Slack is critical for 0
Yhi right he na...
Slack ki theory dekho...3 case h isme
@@StudywithCivilbuddy sir fir Shi answer konsa mane 30th ka ya 44th ka
@@chainsingh3622 44
Sir ques 44 ka answer option b hoga....aapne d btaya
superb sir , majaa aa gaya
Very nice sir
For me helpful for college lecturer 2020
Critical path method
Amazing video sir.. this video actually clear my all doubt and concept 👌
btech ke liye pdh rhe ho kya
@@sangeetakushwaha9063 yes
@@monikabasetiya1500 waste and by product utilization ke question bhi h kya apke pass please yr btai mujko bhi
@@sangeetakushwaha9063 waste management ki subject 5th semester me thi yrr
Abhi to McQ base koi content nhi h es subject se related to yrr
Nhi to will definitely share with you
Aapke pass PROJECT PLANNING se related ho to share kr dena plz
sir aapne lecture me kaha tha k free float depends on succeeding activity to q.28 me preceding ans kaise ayega????
free float ki definition h ki amount of time by which activity delayed without affecting Succeeding activity. lekin question m pucha h ki free float can affact? wo aise nahi puch rha ki kispe depand karti h. bro I may be wrong, agar m galat hu to batana muje..
30 d
In PERT we talk about event not activity
Sir u are genius.
Question no 30.....pert is event oriented not activity oriented...so what will be the right answer???
Event oriented hona chahiye sahi ans🤔
clear explanation needs...
Great sir ji. 🙏
Please upload more videos sir.
it's really enough for Je ,, thanks 😊
SIR QUE 28 ME SUCCESSOR ACTIVITY HOGA AND QUE 44 ME B OPTION HOGA
Yesss sir ne hi last video me succeeding bataya tha,,,,, aur ab preceeding,,,,,,,,,plzzzz clear right one of both.??
@@harishjorwal2466 NOW CLR
28 _ FREE FLOAT ME SUCCESSOR AFFECT NHI HONA CHAHIYE PRECEDER HO SKTA H
44_ SLACK ME EVENT MINIMUM OR ZERO HONA CHAHIYE NA KI ACTIVITY
Q no 28 me
Free float- An activity can be delayed without affecting EST of succeeding activity likhwaya tha..means succeeding activity pe koi affect nhi pdega..so B is the right answer
@@harishjorwal2466
Predecessor ko affect krta h
Successor ko nhi krta.... Yahi 100% correct h bro
Q 30. Ans is D, not B
30 and 44 no. Questions are same but your ans and concept are different
Slack tym is for events not for activities so answer will be D..
It was fun learning with you
In last vedio question number 30 and 44 both are same but your answer is different for same question, plz clarify right answer sir
ultimate lecture sir ji
Thanks sir ji
gajab content keep it up
24 me owner
Sir in lecture 4 video you said that Free float depnds on Succeeding Activity, But in this video Qn no. 28 you said that free float affects Preceding activity....Which one is correct sir ??
free float does not affect succeeding activities means does not depends upon succeeding activities and in question 28 it is asked that free float depends on so it affects or it depends on preceding activities not succeeding activities
Sir ne bola tha ki depend krta h free float succiding activity pr....free to preceding ke liye hua na...
Amazing concept sir amazing
NYC voice and confident looking sir
You prolly dont care but if you guys are bored like me atm then you can watch pretty much all of the new movies and series on InstaFlixxer. I've been binge watching with my girlfriend for the last couple of weeks :)
@Seth Jacob yea, have been using InstaFlixxer for months myself :D
Sir LPP ke lia bhi aesa Previous yr exam wala video upload kar wao
Question no 30 & 44 same h lekin answer alg alg diye h h .
1(b)event
2(d)0
3(d)all of the above
4(d)2
7(c)0
Thank u sir 🙏🙏
And sir aap jo bta rahe ho wo particular activity k liye hota h..... Float < 0....super critical activity
Float=0..... Critical activity
Float>0.... Sub critical activity
Perticular activity critical and path critical.... Both are different..... Detail numerical se ye doubt clear kro
Great👍 explanation sir
thanks sir ji very much
Sir rtu ke liye ppcm ka objective video banao please
Bhai 30 aur 44 questions same pr Answer Alag Alag q bata rhe ho .. Slack time in pert is minimum for critical event ..slack depends event not activity..
Irrigation MCQ
sir, in question no. 14 b & d both options are correct as you have taught us.
No.1 hai sir
critical activities kai lie 0 hi to btaya hai sir apne q. no 44 ka btao sir????
iske phl bhi ye same qstn hai q no. 30 usme to apne 0 hi correct mana hai to 44 mai glt kyu???
Thank you so much sir 🙏🙏
Bahut kuch sikhne ko mila ❤
24 question ka answer kya hoga??
@@engineerpoojajorwal jo idea deta hai woh owner deta hai.... Jo design tyar krta hai woh engg krta hai.... Jo building construction krega according to engg design woh Contract hota hai
Ho gya clear 👍
EA ki book me answer contractor diya hai youth publication me engineer,, esliye confusion tha
@@engineerpoojajorwal maine Construction Management ki book se padi thi sabhi ki definition
Eagle Jagroop singh (Diploma book)
C nhi hoga slack less than o ho skta hai ,, book me bhi b hi hai ,,yha Option b me critical event hona chiye tha slack pert me use hota hai ,,
Wow nice classes
Ye free float kis pr depend krta ha or kisko affect krta ha sb locha ho gya ek video me alg alg ans ab final kya yad kre
👌👌
24. Engineer responsible hota hai
24. Owner
24..aaaaa owner
Question no.30 and 44 are same but answers are different..
Please clarify
Ans is B
Question 30 answer will be D becoz slack is for events not for activities
As per made easy notes and my QT book
Critical path has minimum slack,
Why this 0
hlo sir 50 ka ans B to ni hoga , and unlimted resources resources levelling me hote hai, isiliye uska duration non changeable hota hai
Amazing !!
Great sir keep it up
Great sir
Tnku sirji..🙏
Q 44 B
❤
Nice sir
thank you soo much sir
24(owner)
Kya sir aap ne 28 bale question me btaya ki free float Preceding activities pr defend krta h Or phle jb total float btaya bha apne kha ki free flaot succeeding activities pr defend krta h... Ye kya h sir khud hi apni baato se ese confusion peda krte ho or pir hum bi yha bete bete confusion peda kr lete h mind me pir question galat hote h toda dyan se pdaya kro sir hume jo aap pdayege bhi krke aane bale h Esliye plzzz toda espr dyan de
Superb
Mcome sem 3 ka lesson saab ptayai na plz
Sir syallbus khatam Ho gaya hai
CPM AND PERT KA
RSMSSB JE ke liye itna he kafi h
sir, apne pert m beta distribution likhaya hai or cpm mai normal distribution TABLE mai to fir ye qstn no. 41 mai ans galat btaya hai apne ya notes mai ulta likhaya hai sahi kisko manu...??????
Pert beta distribution and based on probabilistic approach
CPM normal distribution and based on deterministic approach
Q 6 wapas se batao
Thanks sir
24.owner
Hiii
🙏
24th A
44th D
45 no c
Sir qstn 16 may shyd c hoga
Question no. 30 wrong kaha aap na
Sir, what is the answer of question no.23
Owner or other
Plz confirm it
3.5 days ..💯🔥🔥🔥🔥
Aap jo puch rahe ho vo 24 h
24 ka ...aaa owner