[플랜트교육] ITP Witness & Hold 차이점 초간단 설명 ~!!! Inspection and Test Plan Review Witness Hold Differences

Поделиться
HTML-код
  • Опубликовано: 11 сен 2024
  • There are two important inspection action codes in the Inspection and Test Plan they are called witness point and hold point. Few or many had been a little confused about these inspection action codes.
    The Witness point and Hold point are always found and indicated in the Inspection and Test Plan. They are the construction stages that may need supplementary inspection or verification.
    The purpose is to make sure construction specification requirements have complied accordingly and to proceed for the following activities. So the Verification process is outlined and documented in the Inspection and Test Plan as Witness Point and Hold Point.
    Here is the best definition of Witness Point and Hold Point:
    Hold Point is a mandatory verification point beyond which work cannot proceed without approval by the Engineer or Consultant or Municipality Inspector. The work cannot proceed until the Engineer or Consultant is able to verify the quality of the completed work and releases the Hold by means of Inspection Request approval.
    Witness Point is an identified point in the process where the Engineer or Consultant may review, witness, inspect method, or process of work. The activities, however, may proceed.
    Here is a sample of Hold Point:
    Example no. 1
    Hold Point: The first floor of our project is to be cast but it must be inspected by the Municipality Inspector before it will be poured with concrete. The Hold Point there is the inspection or verification of the Municipality Inspector; once the Inspection is approved it will release the Hold.
    Example no. 2
    Waterproofing membrane to be applied on foundations. The material must be approved first by the engineer before the construction team can use the material.
    So, the waterproofing works cannot proceed without prior approval of the material submittal for waterproofing. The hold here is the approval of the consultant for the waterproofing Material Submittal.
    Example no. 3
    The municipality approval for the submitted structural drawing for the slab. If there is no approval from the municipality you cannot start the work meaning the hold is from the municipality building official.
    Example no. 4
    The floor tile color and dimensions, you cannot start installing or procuring without the client approval. The color and dimension must be approved by the client, so once the color and dimension of tile are approved then the material submittal will then be in status A or B. So, the hold there is the approval of the client.
    Here is a sample of Witness Point:
    Example no. 1
    Witness Point: We were on painting activities for a second coat, the Inspector just witnessed the applications of coatings.
    Example no. 2
    The blockwork or block wall installation inspection. The consultant may not attend the inspection but the work on site can proceed and continue.
    Example no. 3
    The surface preparation prior to the application of waterproofing on wet areas. Let say in one floor there are 30 wet areas. So the consultant may either go to the site to see to it if the floors are cleaned or just ask from the quality engineer to check and provide documentary photos for the consultant.
    Example no. 4
    The inspection for plastering. The engineer or consultant sometimes will just conduct the surveillance or rely on a qaqc engineer to check and provide documentary photos.
    What is Witness Point?
    Witness Point is an identified point in the process where the Engineer or Consultant may review, witness, inspect method, or process of work. The activities, however, may proceed.
    What is Hold Point?
    Hold Point is a mandatory verification point beyond which work cannot proceed without approval by the Engineer or Consultant or Municipality Inspector. The work cannot proceed until the Engineer or Consultant is able to verify the quality of the completed work and releases the Hold by means of Inspection Request approval.
    #에듀넷#티클리어#대학온라인강의#에듀윌#ebslang#ebsi#해커스#elihigh#기술사#플랜트엔지니어#플랜트산업협회#KOPIA#한국조선해양플랜트협회#한국플랜트학회#산업통상자원부#한국엔지니어링협회#삼성엔지니어링#삼성물산#대림건설#대우건설#한국가스공사#롯데건설#롯데케미칼#해외취업#sk에너지#sk화학#한화건설#SK건설#GS건설#현대엔지니어링#현대건설#ARAMCO#TOTAL#BECHTEL#금속재료#upstream#downstream#onshore#offshore#용접기능사#용접기능장#용접산업기사#용접기사#특수용접#용접기술사#플랜트교육#플랜트강의#해외건설#해외프로젝트#KOCW#수능강의#수능강의#수능인강#중등인강#메가스터디#1타강사#수능특강#산업인력공단#특강#수능특강#일타강사#검정고시#추천인강#화공플랜트#발전플랜트#해양플랜트#DT#EPC#배관기초교육#배관정복#배관강의#배관강좌#플랜트학과#무료교육#무료강의#온라인교육#국비교육#국비무료#플랜트산업#중동취업#해외취업#국비지원무료교육#억대연봉직업#마이스터고#폴리텍대학교#기계공학과#화학공학과#KAIST#itp#inspection test plan#wps#pqr#application#acceptance#criteria#subcontractor#contractor#company#client#asme b31.3#asme sec ix#review#witness#hold#itb#invitation to bidder#bidder#project contract#검사방법#검사주체#입회#서지검토#서류검토#합격기준#acceptance#fitup#welding#ndt#radiography#pwht#hydrotest#pressure test#pneumatic test#weld#repair

Комментарии • 11

  • @로토-p6i
    @로토-p6i 3 года назад +2

    김소장님 영상은 진짜 이론과 실무에 대한 내공이 느껴짐 얼른 번창하셔야 하는데ㅠ항상 감사합니다

    • @plant_kim_CM
      @plant_kim_CM  3 года назад

      채널에 관심 가져주셔서 고맙습니다.
      채널 홍보가 아직 많이 부족합니다.
      많은 분들이 볼 수 있도록 주변 지인분들과 공유하시면 더욱 좋겠습니다. 감사합니다.

  • @user-wo4yd2eg7s
    @user-wo4yd2eg7s Год назад +1

    감사합니다 :)

    • @plant_kim_CM
      @plant_kim_CM  Год назад

      좋은 댓글 고맙습니다.
      채널공유로 좀 더 많은 사람들이 볼 수 있다면 더욱 좋겠습니다.
      감사합니다.

  • @TV-lw9gq
    @TV-lw9gq 3 года назад +1

    키야~ 주제 선정 조타~

  • @user-tw7ev8dv2o
    @user-tw7ev8dv2o Год назад

    유감이지만, 제 동료들이 이런거 관심이나 있을까요? ㅋㅋ
    저는 EPC업체에 시공경력자로 가고싶은 놈이니까 공부하는거고 ㅋㅋㅋㅋㅋ

  • @user-mt8mv7me6f
    @user-mt8mv7me6f 3 года назад +1

    MDR에 대해 한 번 만 교육 부탁드립니다.

    • @plant_kim_CM
      @plant_kim_CM  3 года назад +2

      좋은 댓글 고맙습니다.
      MDR이란 품목이 Code 요건에 따라 만들어졌음을 인정하는 문서이다.
      이와 관련된 도움이 될만한 블로그 소개해 드립니다.
      blog.daum.net/asgi2/18353528

    • @user-mt8mv7me6f
      @user-mt8mv7me6f 3 года назад +1

      @@plant_kim_CM 감사합니다.

    • @plant_kim_CM
      @plant_kim_CM  3 года назад +1

      많은 분들이 볼 수 있도록 주변 지인분들과 공유하시면 더욱 좋겠습니다. 감사합니다.