What is Hold Point, Witness Point And Surveillance Point in Inspection| Inspection And Test Plan.

Поделиться
HTML-код
  • Опубликовано: 17 ноя 2024

Комментарии • 28

  • @syedanwarali5445
    @syedanwarali5445 Год назад +3

    Very Well explained. I was to much confused about ITP after watching this video now my concept is 💯 clear.
    Thanks bro for sharing. Keep it up

  • @smartsayed143
    @smartsayed143 Год назад +1

    Thanks for sharing these kind of information.

  • @abbas6023
    @abbas6023 Год назад +2

    Thankyou brother's for this information.

  • @chinnathambiselvarajan3603
    @chinnathambiselvarajan3603 11 месяцев назад +1

    👍👍👍👍

  • @abidkhan9019
    @abidkhan9019 6 месяцев назад +1

    Great

  • @taofeekadebayosalam7157
    @taofeekadebayosalam7157 Год назад +1

    Please I want you to enlighten us on Audits. Thanks

  • @HABIBULLAH-mu3gd
    @HABIBULLAH-mu3gd 8 месяцев назад +1

    Please create video on Lead auditor,

  • @altafKhan-fy1bu
    @altafKhan-fy1bu Год назад +1

    Really bro love you

  • @AdilKhan-zg7jy
    @AdilKhan-zg7jy Год назад +1

    Sir make a video which document required before concrete casting

  • @jamalhussain9806
    @jamalhussain9806 Год назад +1

    Assalamualaikum brother

  • @m.shahidkhan0199
    @m.shahidkhan0199 Год назад +1

    Bro can now you can tell me about QCR

  • @noorullahkhan8516
    @noorullahkhan8516 Год назад

    Nice bro

  • @ecomeguru5641
    @ecomeguru5641 6 месяцев назад +1

    aoa,
    sir plz explain review point
    thanks

    • @CivilEngineerAtSite
      @CivilEngineerAtSite  6 месяцев назад +2

      Before starting any activity we have to submit Method of statement, material approvals, shop drawings etc. All these documents should be reviewed by consultants and contractors. It’s called review point.
      We use review point for documents review

    • @CivilEngineerAtSite
      @CivilEngineerAtSite  6 месяцев назад +1

      Before starting any activity we have to submit Method of statement, material approvals, shop drawings etc. All these documents should be reviewed by consultants and contractors. It’s called review point.
      We use review point for documents review

  • @arbaazansari4197
    @arbaazansari4197 6 месяцев назад +1

    AOA,
    How do you decide which activity is hold point or witness point or surveillance?

    • @CivilEngineerAtSite
      @CivilEngineerAtSite  6 месяцев назад

      From specification (Client requirments)

    • @akramullah7084
      @akramullah7084 13 дней назад

      Means that in client specifications each activity is mentioned that's it is hold activity.witness activity etc​@@CivilEngineerAtSite

  • @arabvibes4620
    @arabvibes4620 Год назад +1

    Brother these 3 points also called level of inspection???
    Please guide me..

  • @saleemtarhana4754
    @saleemtarhana4754 8 месяцев назад +1

    How many categories WIR

  • @naqashnawaz2041
    @naqashnawaz2041 Год назад +2

    What is Review point its is also like surveliiance point .

  • @samtupolov2166
    @samtupolov2166 2 месяца назад

    I can not understand what you say, please try to pronounce words with less accent