  • Blue line updates from Hebbal to Kasturinagar. Recorded Date : 12-May-2023
    Phase 2B - Hebbal to K R puram
    ***********************************************
    May 2023 Updates
    Civil Contractor : PKG1 - NCC LTD - 11.003 KM & 650 metr depot line
    PKG2 - NCC LTD - 11.678 KM
    PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion.
    Piling Works Happening and Pier casting Picking up pace.
    Stations in the stretch :
    Package 1 :
    Kasturinagar Station - Piling Works Done. Pier casting to beging
    Horamavu Station - Pile Cap Works In Progress
    HRBR Layout Station - Piling works and Pile Cap Works in Progress
    Kalyangar Station - Piling Works Done. Pier casting started
    HBR Layout Station - Piling Works In Progress
    Nagavara Station ( Interchage with Pink Line ) - No Works as yet
    Veerannapalya Station - Pier casting yet to begin
    Kempapura Station - No Works as yet.
    ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಕೆ.ಆರ್‌.ಪುರ ನಿಂದ ಕೆಂಪೇಗೌಡ ಅಂತರ್ ರಾಷ್ಟ್ರೀಯ ವಿಮಾನ ನಿಲ್ದಾಣ | ಏರ್ಪೋರ್ಟ್ ಮೆಟ್ರೊ ಎರಡನೇ ಹಂತ-2B

Комментарии • 2

  • @sasmitsanjay9154
    @sasmitsanjay9154 Год назад

    For Nagavara Station, work has been started and progress is considerable. The station is underground.

    • @SunilHP
      @SunilHP  Год назад

      That is pink line - reach 6 and not the airport line station. Airport line- blue line station is between the split flyover on ORR