Bangalore Metro : Blue line : Airport line : Hebbal - K R Pura : May 2023 Updates
HTML-код
- Опубликовано: 11 май 2023
- Blue line updates from Hebbal to Kasturinagar. Recorded Date : 12-May-2023
Phase 2B - Hebbal to K R puram
***********************************************
May 2023 Updates
Civil Contractor : PKG1 - NCC LTD - 11.003 KM & 650 metr depot line
PKG2 - NCC LTD - 11.678 KM
PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion.
Piling Works Happening and Pier casting Picking up pace.
Stations in the stretch :
Package 1 :
Kasturinagar Station - Piling Works Done. Pier casting to beging
Horamavu Station - Pile Cap Works In Progress
HRBR Layout Station - Piling works and Pile Cap Works in Progress
Kalyangar Station - Piling Works Done. Pier casting started
HBR Layout Station - Piling Works In Progress
Nagavara Station ( Interchage with Pink Line ) - No Works as yet
Veerannapalya Station - Pier casting yet to begin
Kempapura Station - No Works as yet.
ಬಿಎಂಆರ್ಸಿಎಲ್ | ಕೆ.ಆರ್.ಪುರ ನಿಂದ ಕೆಂಪೇಗೌಡ ಅಂತರ್ ರಾಷ್ಟ್ರೀಯ ವಿಮಾನ ನಿಲ್ದಾಣ | ಏರ್ಪೋರ್ಟ್ ಮೆಟ್ರೊ ಎರಡನೇ ಹಂತ-2B
For Nagavara Station, work has been started and progress is considerable. The station is underground.
That is pink line - reach 6 and not the airport line station. Airport line- blue line station is between the split flyover on ORR