Siruseri - Sozhinganallur Metro Work ! Corridor 3 ! Extension to ECR Road ?
HTML-код
- Опубликовано: 7 сен 2024
- Siruseri to Sozhinganallur metro work shared in this video.
This stretch is part of Chennai Metro Phase 2 Corridor 3 of Madhavaram Milk Colony - Siruseri Sipcot. It is elevated section. Contractor : RVNL
For the past few months metro work stopped in this stretch due to sub contractor issue. Now new sub contractor has been appointed. Hope metro work will resume in full fledge soon.
As of now only pile foundation machine and has been deployed near Semmancheri. Siruseri to Sathyabhama University bus stop barricade work was fully completed.
Sathyabhama University to Sozhinganallur stretch barricade work need to be done.
Siruseri Sipcot 1, Siruseri Sipcot 2, Siruseri, Navalur, Gandhi Nagar, Semmancheri 1, Semmancheri 2, Sozhinganallur laket 1, Sozhinganallur lake 2 , Sozhinganallur are the metro stations will be constructed in this stretch.
bro, your updates are fantastic .. thank you for doing this, great job!
@@gabrielleraul488 Thanks
Super Coverage & Update
Thanks
Kelambakkam - Kovalam is 3.5 KM.
Metro should be extended up to Kovalam Beach.
Kovalam is already a tourist spot. Many foreign tourists visit Kovalam. ECR traffic is also will reduce if Kovalan is connected by Metro.
Tiruporur MLA is sleeping.
Already, New 2nd International Airport planned at Tiruporur is shifted to Sriperumbur (Parandur)
Correct Said Bro
The work just started at small section near college.
This section work was not happening for more than 1 year.
Per latest news in paper there will be delay of 6 months. It's a far fetch.
Hope the OMR section from SRP to Sipcot get complete by 2026 end.
But i vaugely remember how this place was during late 1999. My parents took me to thiruporur murugan temple wen i was studying 5th.... even 2002 ! Apah totally isolated and terribly a outskirt place from city.... proper thar road kuda ella if im not wrong. Oru rented ambassador car... from kknagar .
Kuthambakkam bus terminus present status enna nu video coverage panna try pannaunga
Will do
Please Give us a Update on Broadway Bus Stand Redevelopment and 4th Line Work Between Beach-Egmore. If Possible. Thankyou.
@@vro667 Will do
Bro Pattabiram Railway Bridge Update Podunga.
@@KamalKanth-ji1xw Will try
Why shouldn't metro fine the contractor for delaying things?
They should do. More than that work has to kick start fast to compensate that delay.
2027 dec minimum.... athuku koranju 1% vvaaipu ella. Since this purely driverless metro. After civil construction .. testing matume 3 to 4 months pogum. For sure by 2028 1st quarter this seruseri line will be ready
Bro, Omni bus stand Varadharajapuram chennai status cover pannunga if possible
Will try
This section romba worst bro..perusa no progress at all.Romba delay aagirum ipdi pona
@@saran.seenivasanHope gradually work will be speed up for the delay
Ippp thaan start pannuranga so paakalam but , oru angle la paatha other all finish achu na inga workers nerya add panni work fast ah mudika chance iruku.
At that place only, they are building metro girders
iam from Mohamed Sathak aj college of engineering marina mall opposite but athukula na clg mudichuruva poola😂😂 enum approximate evalo days agum 😊
Approximately 2 years
Bro kilambakkam railway station work process video poto bro
@@djtamilgamer5034 Will do
Poonamalle metro depot full pls update
@@elanchezhiyans2042 Will try
💜💜💜💜
First it was Vandalur Kelambakkam road but was dropped
@@joshuad007 Yes, but there is proposal to extend upto Thiruporur in future
Kamatchi thoraipakkam la thana iruku
@@communication-up6ol Kamatchi hospital located at intersection of Velachery - Tambaram main road & Pallavaram - Thoraipakkam radial road. Located around round 4 km distance from Thoraipakkam signal i guess
Looks like nothing going on..
Currently ... thanks sir
@@karagis75 Yes but couple of pile machine are placed for foundation work near Semmancheri . Gradually work will pick up in upcoming days
@@NambiValavan thanks sir