Chimney Hollow Reservoir 2023 Construction Recap

Поделиться
HTML-код
  • Опубликовано: 9 фев 2025
  • Chimney Hollow Reservoir construction crews wrapped up the 2023 construction season with about 55 percent of the project completed, and remain within about a month of their originally targeted completion deadline of late summer of 2025. In this video, Northern Water and Barnard Construction managers highlight how the main dam has reached 160 feet tall (of its ultimate height of 350 feet) and provide updates on several other elements of the project.

Комментарии • 69