@@MohitRoy-ci3bw The maximum settlement permitted at the head of an individual pile during load testing is 10 mm plus the calculated elastic shortening of the pile shaft, for piles less than 1000mm diameter. For test piles greater than 1000mm diameter a value in excess of 10mm may be appropriate.
Very very nice 😊
Very Nice 😊
Nice video 😃
Good info sirji
Very informative 👍 and perfectly edited
Loved it brother ❤️
Good vedio
Bhai gjb you are the boss
Good Going.. Very well explained...Keep it up ✌🏻
Thank you bro 🥰
@@Engineer-Verse-what is the settlement value permissible?
@@MohitRoy-ci3bw The maximum settlement permitted at the head of an individual pile during load testing is 10 mm plus the calculated elastic shortening of the pile shaft, for piles less than 1000mm diameter.
For test piles greater than 1000mm diameter a value in excess of 10mm may be appropriate.