WSJF - Weighted Shortest Job First prioritisation method
HTML-код
- Опубликовано: 8 сен 2024
- This simple example of scoring is similar to "value for money", however, extended in time, and applies relative estimations, which make it extremely fast and easy to use.
Me and my team can help you with your Backlog estimation and its items prioritisation.
Also read my blog on Agile / agile
This method is originally introduced by Dean Leffingwell, Don Reinertsen, and SAFe (Scaled Agile Framework) here www.scaledagil...
New home for this video will be here ruclips.net/video/9_SXjHGEmaA/видео.html
Absolutely fantastic - best explanation on the online!
Very well explained, thank you.
Hi Mary!
Thanks for your feedback!
Just want to let you know that I'm moving part of the content to my new channel, and this video will live here ruclips.net/video/9_SXjHGEmaA/видео.html
Tnanks for this Dimitiry.
Please can you help me with this potential PMP question
An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price.
What should the product owner do about this situation?
A. Reprioritize the backlog based on value and cost of delay divided by duration.
B. Switch to a predictive approach to prevent any further delays to completion.
C. Reprioritize the backlog based on story size and competence availability.
D. Remove low-value items from the backlog to compensate for the higher cost.