    Cost Breakdown for Superior Walls as of Fall 2023
    QTY DESCRIPTION UNIT PRICE
    TOTAL
    179.30 LF Of 4' Std Panel w/8" top $71.00
    $12,730.30
    42.85 LF of 9' Panel $88.00 $3,770.80
    366.30 LF of 9' X I Plus Panel $103.00
    $37, 728.90
    44.00 Corners $45.00 $1,980.00
    4.00 Special Window Opening $100.00
    $400.00
    2.00 Special Door Opening $125.00
    $250.00
    6.00 Drops $45.00
    $270.00
    12.90 Special Ledge Detail #3 $12.00
    $154.80
    5.00 Beam Pockets w/ 2 x 2 $180.00
    $900.00
    2.00 Beam Pockets w/ 3 x 3 $220.00
    $ 440.00
    20.00 Support Ledges $25.00
    $500.00
    47.00 Floor Ties $3.00
    $141.00
    6.00 Square Footer Pads 3 x 3 Insta $100.00
    $600.00
    1.00 Knee Wall $60.00
    $60.00
    300.00 Garage Bolts $1.00
    $300.00
    1.00 Set-Up $405.00
    $405.00
    1.00 Crane $770.00
    $770.00
    5.00 Freight $705.00
    $3,525.00
    TOTAL $64,925.80
    CAT 315 Rental $6000
    Kubota Skid Steer $4000
    Stone for Foundation Base $17,000
    Felt under Foundation $1000
    Fuel $1200
    TOTAL COST TO HAVE SUPERIOR WALLS SET $94,125

Комментарии • 36

  • @6.7Rollin
    @6.7Rollin День назад

    using them as you speak, walls come in 2 weeks for foundation/ basement! also keep in mind if you like high ceilings its less than a $1000 per foot height. i started with 8' for my basement an quickly went to 10' when i found that out. wanna say it was $830 per one foot higher wall

    • @TodayIWorkOn
      @TodayIWorkOn  День назад

      We wanted 10’ ceilings but the problem for my house was distance and weight. The crane was able to do so far and the 10’ walls would have been an even bigger issue. I’m very happy at 9’. I have 10-18’ ceilings in the 1st floor which is making me busy going up and down ladders, lol. Good luck with the install. If your prep is good, you should be good!

  • @shakejones
    @shakejones Месяц назад +2

    Great video+explanation+presentation! Thank you for sharing your knowledge! Well done mate - NEW SUB 🙏🏻

  • @sflake02
    @sflake02 Месяц назад +3

    Great content, great work ethic, and straight to the point. Subscribed 🎉😂

  • @t.l.fuller95
    @t.l.fuller95 6 месяцев назад +5

    Very insightful. I was quoted $71k for 350LF for 10' Xi Walls.

    • @cashcow4383
      @cashcow4383 6 месяцев назад

      is that installed for the 71k ?

    • @t.l.fuller95
      @t.l.fuller95 6 месяцев назад

      @@cashcow4383 after excavator, yes

    • @darianamendola7153
      @darianamendola7153 5 месяцев назад

      Was this only for the walls?

    • @t.l.fuller95
      @t.l.fuller95 5 месяцев назад

      @@darianamendola7153 Yes

    • @t.l.fuller95
      @t.l.fuller95 5 месяцев назад

      @@cashcow4383 installed, but not the site prep/stone

  • @S2000guy
    @S2000guy 4 месяца назад +1

    you've been putting out some great content

  • @Karasu416
    @Karasu416 5 месяцев назад +2

    Awesome resource. Thank you for the information. Also hell yea northeast pa haha

    • @TodayIWorkOn
      @TodayIWorkOn  5 месяцев назад +1

      Thank you. I’m actually going to meet management at the International Building Show tomorrow. I’m excited to talk to them about my experience with the company and what their feedback is.

  • @Keepnit_100
    @Keepnit_100 3 месяца назад +1

    Great content!!! Thanks for sharing

  • @jhoffmanhomes
    @jhoffmanhomes 3 месяца назад +2

    That’s crazy I build all the time with superior walls. Starting a 2200 sq ft basement with 3 car garage . 37000.

    • @TodayIWorkOn
      @TodayIWorkOn  3 месяца назад +1

      What’s crazy? 😂

    • @jhoffmanhomes
      @jhoffmanhomes 3 месяца назад

      @@TodayIWorkOn your cost

    • @fsl4346
      @fsl4346 Месяц назад

      The question is, how long ago was that?

  • @cashcow4383
    @cashcow4383 6 месяцев назад +1

    love the videos.

  • @THENEWMAJORITY
    @THENEWMAJORITY Месяц назад

    Thanks!

  • @t.l.fuller95
    @t.l.fuller95 6 месяцев назад +1

    Thank you

  • @fsl4346
    @fsl4346 Месяц назад

    Thanks for sharing. My question is why didn't you continue building the rest of the house with it? For strength and greater insulation I would just do the whole house in concrete. But great content. Thanks for sharing.

    • @TodayIWorkOn
      @TodayIWorkOn  Месяц назад +2

      The cost to build a 10,000 sqft house would be something I couldn’t afford in concrete. I’m taking donations though! 😝

  • @jmcglashan1
    @jmcglashan1 3 месяца назад +2

    Great detail. I am talking with SW in western NC. I’m getting quoted $170 LF for a 10’ xi wall totaling 176 LF. I’m scratching my head on how there could be such a price difference from your 9’xi to my 10’xi? How recent is your quote?

    • @TodayIWorkOn
      @TodayIWorkOn  3 месяца назад +1

      August 2023 was my quote.

    • @sparksmcgee6641
      @sparksmcgee6641 Месяц назад

      He got twice as much wall and a lot of things have a set cost per job. It goes down per unit

  • @mayaly356
    @mayaly356 5 месяцев назад +1

    I just started to see your videos as a contractor You do a good job ,But when did you make the ground floor slab, because I noticed that you completed the wooden first floor before pouring the concrete slab

    • @TodayIWorkOn
      @TodayIWorkOn  5 месяцев назад +1

      Correct. I was going to pour the basement slab first but I had a 3 week wait for the lolly columns and decided to build the deck while waiting for the columns. Once I had the columns I was able to pour the basement floor. I’ll be going all over this in my build videos.

    • @mayaly356
      @mayaly356 5 месяцев назад

      @@TodayIWorkOn All my best wishes for your successful progress. We are following you with interest

  • @johnlynes4453
    @johnlynes4453 18 дней назад

    Is it possible to get the 3" waste stacks into the superior wall cavity or do you have to fir out a box to go around the pipe to get it into the floor joists above?

    • @TodayIWorkOn
      @TodayIWorkOn  18 дней назад

      Nope. It would have to be boxed out. It’s the foundation wall.

  • @sparksmcgee6641
    @sparksmcgee6641 Месяц назад

    Thats crazy high if youre going to build your own house.
    Look up Thermomass and then rent commercial concrete forms. Theyre easy to use.
    You are wrong about the price, saying you know its more for a poured wall even though you didnt price it.
    These are like all prefab and its sold as low labor and quick set.

    • @TodayIWorkOn
      @TodayIWorkOn  Месяц назад

      What’s exactly “crazy high”? Concrete has skyrocketed in price since covid. After being in the trade for a long time, I’ve always liked the idea of superior walls because it’s a great system. A 6100 sqft foundation is big money in block or forms. My friend that built a 12,000 sqft house with a 4500 sqft basement with a pour spent over 120k on the pour. Talking to my local concrete guy that does block foundation told me there was no way he would be able to touch the cost of the superior walls and the time it would have took to lay the block would have taken quite a while. I had no desire to rent commercial forms and set up a 28 corner concrete wall system. That would set me up for failure. 😂. Low labor and quick set is a great option. Time is money. R21 insulation is awesome. Level from 140’ from one side to the other is awesome. Etc. You should look a little deeper into this system than just writing it off.

    • @sparksmcgee6641
      @sparksmcgee6641 Месяц назад

      @TodayIWorkOn Go look at the product I mentioned and price out that way. I'm guessing the savings is about half the cost. Guessing that amount can guarantee labor shows up.

  • @micharris1761
    @micharris1761 5 месяцев назад +2

    you must own a bank lol

    • @TodayIWorkOn
      @TodayIWorkOn  5 месяцев назад +3

      🤣🤣. If I owned a bank I would be sipping old fashions in Florida instead of freezing my ass off doing most of the work myself. 💀. Building is expensive in 2024.