Chennai Beach to Chennai Egmore 4th line update as on 12/01/2025
HTML-код
- Опубликовано: 7 фев 2025
- Chennai Beach to Chennai Egmore 4th line update as on 12/01/2025 #indianrailways #train #railfans #railway #chennai #chennaitrain #egmore #egmorerailwaystation #park #chennaibeach
Special thanks for this latest update as on 12.01.2025 ie today. Island Platform at Park Station is nearing completion hence some portion of track is to be laid here. I think in another 15 days time all work may be over. Fully loved and enjoyed this digital travel with you. All the best. Take care.
@@s.v.kumarkumar5204 Track is fully laid, only platform work and track packing is pending..
Thanks for sharing long pending work status.they would have extended the platform towards beach side inland platform between 3 & 4th side enough land space is available. Anyway the project going to complete verysoon 😊.
@@sathishkumars6830 I too thought this which can handle Express trains in case of special trains from Chennai Beach..
superb progress in park station short PF for 4 and 3 tracks. thanks
Thanks.... Excellent update regarding track work.. waiting to see when they will be open this stretch
Thanks for the update❤
Thanks for your update 🙂
Thanks for update
good update congratulations
Please upload another video.
When we can expect the next update in this same line 😊
Thank you for the update bro 😅
No problem 👍
Today you will upload
Good
By march. The line will be open. For public
@@mnivarathan Mostly by February Month
Is the track work at the island platform completed?
Track laying is fully completed.. only platform work and track packing is pending..
Sir when crs
@@madhialaganbalu2741 May be first week of February..
tv is repeat to repeat.
tv is repeat to repeat.