Greg, Excellent video and a very good commentary with it. I saw lots of piles close to the site boundary with the pile beam sitting top of it. Is this to create the boundary or the strength to the building structure? The CBR test was shown brilliantly which is a top requirement for the Structural Engineer. Does the CBR test result decides how much capping layer in millimetre is required? Super video. Congratulations.
Hi, thanks for this lovely video. I was just wondering, how do you progress with the piling work with the geogrid underneath? Do you cut out the geogrid in the areas where you pile? or would the rig tear right through it? Thanks!
Hi Erkan! I am not sure about the thickness of that one and I think there was 1 layer of geogrid. It all depends on soil condition survey and the later design.
Got the questions, where usually testing pile has to be installed, and for what purpose. Second question , does pressure testing need to be applied always? Or you can just say “solid as fuck” ground
They are installed to check/confirm the bearing capacity of the pile in the ground (confirming the ground investigation survey).To check the pile pressure has to be always applied, you can see in my next video, I will also cover this bit more in Construction Drawings video nr.3, showing the results.
This series of videos are really good hopefully you keep up loading more over coming weeks
Thank you Gamer, I promise I will do :)
Loved the series, please keep uploading. Some intriguing enginuity with that CBR test :)
Thanks Donald, will do!
Very useful as I will be starting as a graduate engineer.
Great! Wish you all the best and if I can help let me know :)
Awesome, I always wanted to know or see how this was done. Thank you.
I’m happy you enjoyed 👍👍
Great video. Keep up the fantastic work. Subbed
Thanks for the sub!
It's fascinating!!
Happy you like it !
Greg,
Excellent video and a very good commentary with it.
I saw lots of piles close to the site boundary with the pile beam sitting top of it.
Is this to create the boundary or the strength to the building structure?
The CBR test was shown brilliantly which is a top requirement for the Structural Engineer.
Does the CBR test result decides how much capping layer in millimetre is required?
Super video. Congratulations.
Thank you Asim! Happy you like it :)
Hi, thanks for this lovely video. I was just wondering, how do you progress with the piling work with the geogrid underneath? Do you cut out the geogrid in the areas where you pile? or would the rig tear right through it? Thanks!
Thanks! Happy you like the vid! The rig goes through it 👍
Well done
Thanks :)
What was the piling mat thickness and how many layers of geogrid?
Hi Erkan! I am not sure about the thickness of that one and I think there was 1 layer of geogrid. It all depends on soil condition survey and the later design.
What is the minimum cbr value for piling mat
This is dependent on what machinery will be operating - a piling rig
God be with you
I am looking for a job how can I communicate with you?
Hi Alilat! My job is getting quiet and I might be looking for a job soon :) Try CV library and go to construction sites and ask, that's the best way.
Got the questions, where usually testing pile has to be installed, and for what purpose. Second question , does pressure testing need to be applied always? Or you can just say “solid as fuck” ground
They are installed to check/confirm the bearing capacity of the pile in the ground (confirming the ground investigation survey).To check the pile pressure has to be always applied, you can see in my next video, I will also cover this bit more in Construction Drawings video nr.3, showing the results.
Hi brother
Hi!!
@@SITENG how are you
@@shankarbk4111 I am good, how are you?
Hello
Is there work with you?
whatsapp number
I am not working myself yet 😁 You will know when I am back working on the channel 😁