2 men can complete 5sqm per day..put it into equation....2 x 8 divide 5 =3.2sqm. say 3.5!!! paglake productivity pag bagal pag liit value productivity pag bilis I hope n gets mo ...pls watch other videos regarding productivity.tnx...ps. back to back yun. 3.5 manhourper sqm.!!!!!if your in doubt pede ka mag search ng iba productivity kc what i used is based on my experience!!!!I hope nasagot ko.
ung kalahati ng stud pasok sa 1m square na area ung kalahati nasa labas...!sana nasagot ko tanong mo!....ahhh watch mo uli video para ma gets mo explanation>>>>
and also what im trying to teach is the way to derive. if you have other elements to consider then you incorporate it in your own derivation>>>i hope you get my point!!!!
ung 1.2 to 1.3 un ang ginagamit na multiplier...ibig sabihin patungan ung direct cost para sa profit at overhead 20% to 30%...ok.watch mo other videos naduon explanation ko.
naka specify na sa video ...ung contractors price...syanga pala dapat pag nag dederive ka cost dapat updated sa latest na material price at minimum wage..pls. review the video and analyse carefully...wag mo apurahin...review ng review lang ok!!!
@@marcozapanta738 bak 2 bak na yan!!!!pero ung 312php ...baka di na yan pasok sa presyo ngayon...kc ung price increase... kaya ko tinuturo ito...e para matuto magderive hindi umasa sa result ko sa video na eto...magderive ka un ang point ko!!!i hope na gets mo!!!review mo video to fully understand the procedure!!!
Pano po ang pag compute ng output per hour? Pano nyo po na naderive yung 3.5 man hour per square meter?
2 men can complete 5sqm per day..put it into equation....2 x 8 divide 5 =3.2sqm. say 3.5!!! paglake productivity pag bagal pag liit value productivity pag bilis I hope n gets mo ...pls watch other videos regarding productivity.tnx...ps. back to back yun. 3.5 manhourper sqm.!!!!!if your in doubt pede ka mag search ng iba productivity kc what i used is based on my experience!!!!I hope nasagot ko.
Good day, Sir. Baka meron po kayong price per square meter ng Metal Mesh with Tubular Frame. Salamat po.
pwede mo e derive!!!gamitin mo lang ung principle at system sa mga videos ko...
hello, may I ask kung bakit tig-kalahati lang yung dalawang studs?
ung kalahati ng stud pasok sa 1m square na area ung kalahati nasa labas...!sana nasagot ko tanong mo!....ahhh watch mo uli video para ma gets mo explanation>>>>
Hello, ask ko lang. Ito bang per SQ.m. estimate guide is kabilaan na Ng hardiflex?
1/2.88=0.35 one side x 2 is 0.7pc.
Hello sir, di kasama sa costing mo yung metal track?
ang assumption ko e pati ung metal track e studs na rin...gets mo????
.kulang ng metal track??
ang assunption ko e studs na rin...pwede yun.GETS????
and also what im trying to teach is the way to derive. if you have other elements to consider then you incorporate it in your own derivation>>>i hope you get my point!!!!
sir tanong po saan nakuha yung 1.2 sa cotractor price?
ung 1.2 to 1.3 un ang ginagamit na multiplier...ibig sabihin patungan ung direct cost para sa profit at overhead 20% to 30%...ok.watch mo other videos naduon explanation ko.
thank you sa clear explanation sir@@axcelengineering
Pag pakyan po mag Kano ang per square meter
naka specify na sa video ...ung contractors price...syanga pala dapat pag nag dederive ka cost dapat updated sa latest na material price at minimum wage..pls. review the video and analyse carefully...wag mo apurahin...review ng review lang ok!!!
Good day Sr..@@axcelengineeringyung 312 labor per sqm po ba na sukat back to back na po yun pag kinontrata yung drywall salamat po sa sagot😊
@@marcozapanta738 bak 2 bak na yan!!!!pero ung 312php ...baka di na yan pasok sa presyo ngayon...kc ung price increase... kaya ko tinuturo ito...e para matuto magderive hindi umasa sa result ko sa video na eto...magderive ka un ang point ko!!!i hope na gets mo!!!review mo video to fully understand the procedure!!!
@@axcelengineering salamat po sa respond👍