  • Construction on the 3.5-kilometres of elevated viaduct for the 23-kilometre Western Sydney Airport metro line is taking shape with nearly one kilometre of viaduct now constructed.
    The foundation for a new sky-high metro station at Luddenham is also complete and ready for work on the station build to commence next month.
    Luddenham Station is one of six new stations for the metro railway line that will become a crucial connection for people visiting the new international airport.
    Situated up to 13.5 metres above ground, Luddenham Station will be the only station located on a viaduct.
    Three viaduct structures make up the combined 3.5-kilometre section of the alignment that will take metro services over key locations like Blaxland Creek, the Warragamba pipelines and Luddenham Road.
    More than 1,100 segments will be manufactured on the NSW Central Coast for the viaduct structures, which will be supported by 84 piers located every 28 to 40 metres.
    Work will commence on the Luddenham Station build next month with a concrete pour to form the station.
    When complete, Luddenham Station will deliver a rail service to the future research, innovation and commercial precinct in Luddenham and provide world-class travel for people in an area with limited public transport options.
    The works encompass the civil infrastructure necessary for the construction of the track and includes:
    3.5 kilometres of elevated viaduct at Orchard Hills and Luddenham.
    6.7 kilometres of earthworks for track formation.
    A 190 metre long rail bridge over the new M12 motorway.
    A 20 metre long rail bridge within the airport.
    Temporary and permanent access roads.
    Bulk earthworks for the stabling and maintenance facility site.
  • КиноКино

Комментарии • 9

  • @ronvorbach1464
    @ronvorbach1464 5 месяцев назад +1

    Thankyou for your update here. Due to negative coverage in the general media I thought work had slowed but now thanks to you I find the general media is more out of date.

    • @colindobson4045
      @colindobson4045  5 месяцев назад

      Yes, it's definitely not slowed at all thanks for watching cheers col 👍

  • @mitch19636
    @mitch19636 5 месяцев назад +1

    Good stuff Colin; Thanks, mate.

  • @danielmorrisonrhymes
    @danielmorrisonrhymes 5 месяцев назад +1

    Great video, and great soundtrack

  • @RAM_845
    @RAM_845 5 месяцев назад

    Tunnelling for both St'Marys and Bradfield almost done so soon they should start laying down the tracks.

    • @colindobson4045
      @colindobson4045  5 месяцев назад +1

      At 1.07 in the video you can see the ballast being ready to lay down for the tracks I think most of the work will be finished by the end of this year

    • @RAM_845
      @RAM_845 5 месяцев назад

      @@colindobson4045 the small metal curved rebars? That's ready for the rails?