New Foundation for the Pottery Studio
HTML-код
- Опубликовано: 30 май 2024
- Hey folks,
This videos shares a super short update regarding studio construction.
Week 1 of our project, Demolition, happened during the 13th through 17th of May. After Memorial Day, the building crew started the foundation process. This involved a few days of digging, grading, filling with various materials, rebar construction, and form building. Finally, concrete was poured on the 29th. So, we're 2 and a half weeks into the build. When the concrete has properly cured, the framing phase will start.
Many thanks for following along!
Tony Развлечения