Economic Factors (Solved Problem 1)
HTML-код
- Опубликовано: 11 окт 2024
- Power System: Economic Factors (Solved Problem 1)
Topics Discussed:
1. Load curve and load duration curve
2. Calculation of installed capacity
3. Calculation of average power
4. Calculation of plant load factor
5. Calculation of plant capacity factor
6. Calculation of utilization factor
Contribute: www.nesoacademy...
Website ► www.nesoacademy...
Facebook ► goo.gl/Nt0PmB
Twitter ► / nesoacademy
Pinterest ► / nesoacademy
Music:
Axol x Alex Skrindo - You [NCS Release]
• Axol x Alex Skrindo - ...
One of the best lecturer
Sir, the plant that we are working is generating power meeting the max demand 24/7, 8760 hrs per year. The max demand is 50MW (the contract is to despatch 50MW,=the average demand) the plant generates 50MW 24/7 8760 hours per annum. The plant installed capacity is 60MW of 120x500KW generating unit, where 100x500kW running and 20x500kW on standby for maintenance purpose. In this case, what would be the Load Factor, Plant Capacity Factor, Utilisation Factor?
sir power system stability,fault analysis and load flow ke lectures plz provide kre...it will be really helpful.....
sir the uploaded videos were very helpful....thanks!!!....when can we expect the upcoming videos of this course?
sir your lect for lucture are very useful please upload all subject of electrical engg thanks
very helpful
You are the best
thank u sir
Sir please upload remaining topics... Plzzz
Sir small doubt utilisation factor or use factor is same .then use factor=units generated/plant capacity*no of hours but why this formula you can't explained in this lecture.could you please explain it for my confusion
sir .....waiting for the remaining pwr system videos...plz upload
sir please upload problem in power system using differential equation
sir please add more videos on power system
Sir please upload the next topics..
sir can uw plz upload problem's solution of the book global economics 18th edition ??
Utilisation factor is = maximum/ plant capacity
please upload more videos....
Complete playlist link please
Capacity charge is = average/ plant Capacity
when this series will be completed
And thanks for this vedio
Sir plez upload next topic vedio
sir next video kb tk upload hoga
Load factor is = average/maximum
182U1A0212 may 28
Ok sir
28/05/2020
182u1a0210
182u1a0218
May 28
Ok sir
182u10234
28-5-2020