Fixed Overhead Variances SIMPLIFED | For ACCA MA Students | Specimen exam question #22
HTML-код
- Опубликовано: 14 окт 2024
- Help, tips, and guidance to pass ACCA paper MA. Learn how to calculate and solve the Fixed Overhead Variances from ACCA MA, including expenditure, capacity, and efficiency. I'll share an easy-to-memorize template that will help you solve any Fixed Overhead Variance question, including expenditure, capacity, and efficiency variances. Use this system to help you pass your ACCA MA exam.
************************
Steve Willis ACCA
www.stevewillistraining.com
How to pass ACCA exams
Variance analysis help: how to calculate expenditure, capacity, and efficiency variances
*************************
Find more about fixed overhead variances at Open Tuition: • ACCA F5, F2 - Variance...
Find many other helpful videos on James Wright ACCA / jameswrightacca
Honestly a life-saver.. you've made this so much more simple than my textbook! Thanks a bunch :)
Glad it helped!
Thanks for that. Could I take OB like BqSp? I am fascinated with your way of explanation material. More teaches like you are needed in ACCA world. My respect.
Interesting idea! I prefer keep that as 'original budget' as there is no real link to quantity and if your doing marginal costing, you will just plug that figure in anyway. Thank you for the kind words! good luck on your exam :)
Like this straight forward explanation.
Glad you found it helpful :)
thank u very much ...wish u good luck \in ur future enedeavours
Thank you!
muchisimas Gracias mi cabecita de rodilla, De verdad me ayudaste
HI VERY HELPFUL
Thanks Sir im so grateful😆
Always welcome
Thanks a lot Steve!
Very welcome!
Sir, what if it asked us for fixed overhead volume variance?
Not going to lie this is the most confusing part of the whole MA exam for me, I'm quite comfy with the entire syllabus apart from variances! They make me want to pull my hair out! But seeing this video has already made me feel 90% better haha
Thanks!
I feel your pain! I didn't understand it either when I first had to learn it. Fixed overhead VOLUME is Origical Budget ---> SQSP. The far right, skipping over AQSP, to Original Budget.
Excellent!! Thank you!!!!!!
Hi there--glad it helped :)
Wrote a test today... well i only got my name correct for sure, the rest... i read the question over and over, tried to figure out which numbers go were...
can i use this video for the referance for my acca eam of 2022-2023
Yes. Good luck!
@@SteveWillisACCA thank you
Yes😊
@@tawandasamson3978 are you clear ma
Nice!!
Thanks!
brilliance thnks alot
Most welcome :)
Why wouldn't we just use the form given on ACCA website:
Actual exp - X
Less: Budgeted exp - (X)
Fixed overhead prod-n X
so it will be:
Actual exp: (125000/25000)*24000= 120,000
Budg exp: -125,000
Fixed overhead: 5,000 Fav
Could you please take a look
You can do it that way, just harder to memorize in my opinion. In PM you'll need to know how to do about 15 variances--a system is better, IMHO.
Thank you for the response. The only question - with the method I used above I got the answer 5,000 Fav, but you got 5,000 Adverse - where is my mistake?@@SteveWillisACCA
Thank u
You're welcome :)