ஓரங்களில் தண்ணீர் உட்புகும் வாய்ப்புகள் அதிகமாக இருக்கும்....என்னுடைய project இல் இது போன்ற பிரச்சனையை எதிர்கொண்ட அனுபவம் எனக்கு உள்ளது.... நான் பார்த்த கட்டிடத்தின் அருகில் ஆறு அமைந்து இருந்தது...ஒரு சவாலான வேலையாக அமைந்தது....நல்ல அனுபவம்🙏
In this situation first take earth work required depth, remove the water from pump, mix lime with sand below pcc. Use water proof admixture for pcc. Above pcc use the polythene sheet to avoid rising water table..
Good evening sir we faced the same problem in Tambaram site sir in the site we mark all the coloum and excavate the soil and after we make pump and drain the water one by one and made footing concrete sir it's also give good results
It will lead seggrecation of agreegates, rather you can increase 10% water cement ratio if even after dewatering done, there is continuous seepage in the pit. We did the same for water tank foundation concrete of 1000 cement bags during continuous rainy day as per the chief engineer advice in the year 1994
Sir, I did Concrete in same site Condition Today, Dewatering one side and Pouring M30 by pump in Other side with in 5 minutes water fully Cover the Concrete.
Modhala indha madhiri lake area la veedu katta permission kodutha govt ea adikanum. Apram flood vandha udaney thanni vaduruchu nu kadhara vemdiyadhu... Idellam oru pozhapu..
2019 September ல் Metirial contract ல் கொடுத்த வேலையில் 11 காலம் Jcb யால் பெரிய Size தோண்டி மாலை 5 க்குள் 1.5 ஜல்லி கலவை போட்டு சென்று 7.30 pm க்கு மழை. 2010 ல் அதிக மழை பெய்த நாள். உரிமையாளர் அடுத்து மறுத்தும் மோட்டார் வைத்தும் மீண்டும் மழையில் மண் சரிந்து சகதி. அவசரபட்டு காண்ட்ராக்டர் வேலை செய்து நடுபகுதி காலம் 3ம் தவறான அளவில் நிறுத்தி தொடர் மழையில் உள் அளவுகள் சரியில்லாமல் போனதால் 18 மாதமாகியும் ரூப் போட்டு நிற்கிறது. அதிக செலவிற்கு உரிமையாளரிடம் காசு கேட்கிறார்கள். உங்களை தொடர்பு கொள்ள விருப்பம் நீண்ட நாட்களாக.
ஓரங்களில் தண்ணீர் உட்புகும் வாய்ப்புகள் அதிகமாக இருக்கும்....என்னுடைய project இல் இது போன்ற பிரச்சனையை எதிர்கொண்ட அனுபவம் எனக்கு உள்ளது.... நான் பார்த்த கட்டிடத்தின் அருகில் ஆறு அமைந்து இருந்தது...ஒரு சவாலான வேலையாக அமைந்தது....நல்ல அனுபவம்🙏
As I'm a structural engineer, I insist you to please go for piles. Because of the seepage we need to adopt deep foundations.
Hi Sir. Actually I'm beginner.. so learning from your videos thankyou...😅
Thank-you sir Valka Valamudan
In this situation first take earth work required depth, remove the water from pump, mix lime with sand below pcc. Use water proof admixture for pcc. Above pcc use the polythene sheet to avoid rising water table..
How to place the Polythene sheet above PCC sir?
Can i contact with u sir
இதேபோல் தான் நான் வீடு கட்டும் பொழுது பிரச்சனை ஏற்பட்டது அதில் ஒன்றை இன் ஜல்லி அமைத்து காலம் அமைத்து வீடு கட்டி வருகிறேன்.
Me too faced the same, I did exactly what you said. I used OPC 53 grade for batter results.
I'm facing the same issue at present sir..thanks for sharing the information
Thanks for ur information sir
Sir ethana chemical iruka rod ethana iruka strong forwater
we are also facing same problem.we are planning to do Dewatering and use Bitumen sheet/Water proofing and 9 feet footing.
Good
நன்றி ஐயா
yes sir , I faced this kind of problem in Thoothokudi. I did what exactly you said.
Super sir. Thank you for detailed information
Same feeling sir
Good evening sir we faced the same problem in Tambaram site sir in the site we mark all the coloum and excavate the soil and after we make pump and drain the water one by one and made footing concrete sir it's also give good results
Sir congrate dry ya kalanthu kottalama?
It will lead seggrecation of agreegates, rather you can increase 10% water cement ratio if even after dewatering done, there is continuous seepage in the pit. We did the same for water tank foundation concrete of 1000 cement bags during continuous rainy day as per the chief engineer advice in the year 1994
How to construct septic tank water logging area pls explain
Basement filling redmix use panalama sir
Sir same problem for me water ipdi iruntha building strong ah irukuma sis pls pls tell me
Hi sir same issue from my site also
Is it we can use waterproofing
And what kind of cement we can use OPC. Or PPC
And what grade OPC and PPC use
Good news
Quick setting cement usepannalamey
Sir..I'm a Geotechnical engineer..in porur after 3 meters soft clay upto 10 meters. So pile foundation is better
Sir rebar weld vaipathu ah illai kambi kattuvathu better ah
Sir live va face pannraen sir
We used M25 Auguva seal ultratech concrete for arrest water penetrations
Which cement did u used for this concrete sir? OPC or ppc...?? Kindly confirm
PPC
@@HONEYBUILDERS so kind of you for replying sir thank u so much...!!
@@HONEYBUILDERSsir why used ppc
@@HONEYBUILDERScan you used for OPC 53 grade
bore irrukkum Pothu .minimum water level therichurum. athavachey pre-planned excavation start pannalam
Sir, I did Concrete in same site Condition Today, Dewatering one side and Pouring M30 by pump in Other side with in 5 minutes water fully Cover the Concrete.
Same problem sir
Super sir 👌👍💐💐💐💐
Useful content.
Very good
Sir,,depth kammi aagidume ??minimum earthwork 6' erukanum thaane sir? Pl answer pannunga
Boomi poojai pottapiragu mazhai sir. Ground level ku 1 adi mela varaikkum thanni nikkuthu sir.
Enna pannalam?
Work start pannalama...illa postpone pannalama.?
Same problem sir but work start ayiruchu
5 feet pit la 4 feet water irruku sir
Sir entha mari area la soak pit vacha water earaguma?
Sooooopper sir
Sir ground floorkku msand use pannalama sir illa manal use pannanuma
Anna roof conectarte la kambi crank adikama straight ta vachi concrete pota safe na
பில்லர் குழி தோன்டாமல் பைல் basement போடலாமா
Same problem inour side
Super sir
I sir in our plot there is an rain water after pumping shall we go with normal excavation or pile foundation
பில்லர் தோண்டாமல் பைல் போட்டால் storng ஆ இருக்குமா sir
Enakkum nadanthathu .but minimum water vanthathu.idhil namm kavanikkavendiyathu ethanai floor athai poruthu , foundation depth change ahum
Intha situationku yetha video sir
Sir please explain about the pile foundation sir.
Search our earlier videos. We have done few site videos on pile foundation
same same
Sir ithu Pola saptic tank thanni vantha ena panala
Hai sir I have one dobut sir pile foundation is preferable ah sir in your site?
Sir nanga motor usepannom and one by one colum pottom
Same problem
Sir naan gerugambakam vedu. Katuren.
1 view 1st like I am sir😊
Worthy information sir . Fantastic live experiments . Thank you sir . Like Adventure . Good prevention is better than cure . Best Bonding
காலையில் வாக்கிங் போங்க சார் நீடோடி வாழ்க
SEMA comedy about borewell .I enjoyed sir
Modhala indha madhiri lake area la veedu katta permission kodutha govt ea adikanum. Apram flood vandha udaney thanni vaduruchu nu kadhara vemdiyadhu... Idellam oru pozhapu..
Enakku ethe prachanai than sir
இதேபோல் தான் எனக்கும் உள்ளது இடம் குரோம்பேட்டை
How u will build septic tank in place like this. Because if water comes up in septic tank, what is the solution
2019 September ல் Metirial contract ல் கொடுத்த வேலையில் 11 காலம் Jcb யால் பெரிய Size தோண்டி மாலை 5 க்குள் 1.5 ஜல்லி கலவை போட்டு சென்று 7.30 pm க்கு மழை. 2010 ல் அதிக மழை பெய்த நாள். உரிமையாளர் அடுத்து மறுத்தும் மோட்டார் வைத்தும் மீண்டும் மழையில் மண் சரிந்து சகதி. அவசரபட்டு காண்ட்ராக்டர் வேலை செய்து நடுபகுதி காலம் 3ம் தவறான அளவில் நிறுத்தி தொடர் மழையில் உள் அளவுகள் சரியில்லாமல் போனதால் 18 மாதமாகியும் ரூப் போட்டு நிற்கிறது. அதிக செலவிற்கு உரிமையாளரிடம் காசு கேட்கிறார்கள். உங்களை தொடர்பு கொள்ள விருப்பம் நீண்ட நாட்களாக.
Athanala naan saftic tank thonttala
நான் திண்டு்கல்லில் உள்ள எனது வீட்டுக்கு 720ல் தான் தண்ணி வந்தது. என்னத்த சொல்ல
Pakkathula aeri illa ...🙏neenga nikkurathe aeri dhaa😂😂😂
உண்மை சார் இப்போ என்னோட சைடு ஒன்னு மேடவாக்கம் இதே கண்டிஷன்ல தான் இருக்கு
காலம் இல்லை சார் காளம்
Good catch 😁
Too many unnecessary discussion not to point
Super sir
Sir,super