  • A significant milestone has been reached in Loma Linda University Health’s effort to build new health care facilities by 2020. The foundation slab for the new structure began to take shape on March 25, as 85 concrete trucks delivered more than 5,400 cubic yards of concrete to the building site.
    Trucks arrived at the rate of one per minute beginning at 10 p.m., ultimately delivering 540 loads in 10-1/2 hours. More than 100 workers directed the concrete into place. The March 25 project completed one-third of the foundation for the new hospital towers. The second phase of the foundation pour will take place in April.