Good and clear. If I might add a further thought, I'd say that where the Employer has failed to issue a VO or rejected a legitimate request from the Contractor for a formal VO, that rejected request becomes a claim.
Thanks for the clear explanation on the variation vs claims.However hereby I would like to request you please explain merits & demerits of lumpsum contract for Contractor comparatively to remeasurable contact.
Thank you for sharing, sir. Anyway, I would like to ask a question about Variation and Claim (EOT and/or cost). I guess any variations or changes to the Works usually impacts the original Time for Completion and/or cost. Therefore, in case there's a variation or changes to the Works and to secure the Contractor's entitlement to the Contract and applicable laws, normally the Contractor shall submit 1 (one) formal notice [only for variation] or 2 (two) notices [for variation and in further EOT+cost claim for such variation]? Thank you.
@@QuantitySurveyingStudio So, if the Contractor have VALID variations and the Engineer/Employer acknowledges it, the Contractor does not need to submit Claim Notices?
Thanks for video. My question on which I need your insight is that if BOQ quantities differs for excavation and backfill works differ a lot and Contractor didn’t notice at the time of tendering but when contract awarded and work on site started so contractor mer with this unforeseen huge increase in quantity due to cut and fill. So now contractor is submitting his quantities based on real work executed let’s say 2 million m3 and BOQ quantities or contract quantities was 1 million m3 so what would the claim for this case. Thanks in advance
@sameeraummer5112: Follow your Company's standard templates. If needed, you can also adopt and modify templates from your previous companies or other sources.
Good and clear.
If I might add a further thought, I'd say that where the Employer has failed to issue a VO or rejected a legitimate request from the Contractor for a formal VO, that rejected request becomes a claim.
Thanks for the add in Sir.
@@QuantitySurveyingStudio My pleasure - and no need for the 'Sir'!
And keep up the good work.
@@johnclayden1670 Thanks John. Fortunate to get knowledge from you. Have started following you in Linkedin.
Explained in a Crystal clear way
Thanks
Thanks for the clear explanation on the variation vs claims.However hereby I would like to request you please explain merits & demerits of lumpsum contract for Contractor comparatively to remeasurable contact.
Hi sir
I’m looking your video’s all are very useful for me and make many videos to improve our knowledge. Thank you 🙏 all
Thanks for the positive feedback !!!
Your videos are simple and clear. thank you
Thanks
Your videos are simple and clear.Keep posting such useful videos 👌
Thanks a lot
cleared in a simple way.
Thanks a lot !!
Good and clear informative. Please include delay analysis method
Have explained it in another video on the topic EOT. You can go through the same.
Thank you Sir for clear explanation
You are welcome
Thanks, Good explanation
Glad it was helpful!
Thank you for sharing, sir. Anyway, I would like to ask a question about Variation and Claim (EOT and/or cost).
I guess any variations or changes to the Works usually impacts the original Time for Completion and/or cost. Therefore, in case there's a variation or changes to the Works and to secure the Contractor's entitlement to the Contract and applicable laws, normally the Contractor shall submit 1 (one) formal notice [only for variation] or 2 (two) notices [for variation and in further EOT+cost claim for such variation]?
Thank you.
The notice for variation can include eot also.
@@QuantitySurveyingStudio So, if the Contractor have VALID variations and the Engineer/Employer acknowledges it, the Contractor does not need to submit Claim Notices?
Very useful 👍 appreciate
Thanks a lot
Clearly understand thank you
You are welcome !!
Good lecture Sir
Keep watching
Good one, simple
Glad you liked it
Amazing channel 👏 👌
Thanks a lot !!
Clear 👍👍
Thanks
Nice presentation
Thanks a lot.
Best video bro❤
Thank you so much 😀
Thanks for video. My question on which I need your insight is that if BOQ quantities differs for excavation and backfill works differ a lot and Contractor didn’t notice at the time of tendering but when contract awarded and work on site started so contractor mer with this unforeseen huge increase in quantity due to cut and fill. So now contractor is submitting his quantities based on real work executed let’s say 2 million m3 and BOQ quantities or contract quantities was 1 million m3 so what would the claim for this case. Thanks in advance
It will be a variation.
@zulqarnainsatti6417: In brief, it will be variations (additional works/increased quantities).
If its an additional scope of works such as construction of an ancillary building to the adjacent plot,will it be considered as a variation or claim?
It will be a Variation.
What about damage items by others…
Since it is an unexpected event it can be classified as claim
Does Additional work and claim are same? Because the term“Claim” we used for all the payment request purposes
Additional works means variation from original scope.
❤Best
Thanks
why you dont post any more jobs in your linked in job page?
Was caught up with few works. Will start putting soon.
Any format for submission
Depends on companies and clients.
@sameeraummer5112: Follow your Company's standard templates. If needed, you can also adopt and modify templates from your previous companies or other sources.
can you do a video about cost report please
Sure
Need software
Which ?