Variation & Claim | Are they same or different ? | Interview Question

Поделиться
HTML-код
  • Опубликовано: 6 окт 2024

Комментарии • 60

  • @johnclayden1670
    @johnclayden1670 2 года назад +15

    Good and clear.
    If I might add a further thought, I'd say that where the Employer has failed to issue a VO or rejected a legitimate request from the Contractor for a formal VO, that rejected request becomes a claim.

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  2 года назад

      Thanks for the add in Sir.

    • @johnclayden1670
      @johnclayden1670 2 года назад +3

      @@QuantitySurveyingStudio My pleasure - and no need for the 'Sir'!
      And keep up the good work.

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  2 года назад +1

      @@johnclayden1670 Thanks John. Fortunate to get knowledge from you. Have started following you in Linkedin.

  • @MrWasim148
    @MrWasim148 Год назад +1

    Explained in a Crystal clear way

  • @mohammadumarfarooq675
    @mohammadumarfarooq675 2 года назад +1

    Thanks for the clear explanation on the variation vs claims.However hereby I would like to request you please explain merits & demerits of lumpsum contract for Contractor comparatively to remeasurable contact.

  • @mohamedrifkan4310
    @mohamedrifkan4310 2 года назад +1

    Hi sir
    I’m looking your video’s all are very useful for me and make many videos to improve our knowledge. Thank you 🙏 all

  • @sajajabeer
    @sajajabeer Год назад +1

    Your videos are simple and clear. thank you

  • @159357982
    @159357982 2 года назад +1

    Your videos are simple and clear.Keep posting such useful videos 👌

  • @oRaNgE-ty3fb
    @oRaNgE-ty3fb 2 года назад +2

    cleared in a simple way.

  • @okaygo6196
    @okaygo6196 2 года назад +1

    Good and clear informative. Please include delay analysis method

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  2 года назад

      Have explained it in another video on the topic EOT. You can go through the same.

  • @Boss-wd4hj
    @Boss-wd4hj 2 года назад +1

    Thank you Sir for clear explanation

  • @MrJuzail
    @MrJuzail Год назад +1

    Thanks, Good explanation

  • @alvinsihombing18
    @alvinsihombing18 2 года назад +1

    Thank you for sharing, sir. Anyway, I would like to ask a question about Variation and Claim (EOT and/or cost).
    I guess any variations or changes to the Works usually impacts the original Time for Completion and/or cost. Therefore, in case there's a variation or changes to the Works and to secure the Contractor's entitlement to the Contract and applicable laws, normally the Contractor shall submit 1 (one) formal notice [only for variation] or 2 (two) notices [for variation and in further EOT+cost claim for such variation]?
    Thank you.

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  2 года назад

      The notice for variation can include eot also.

    • @gianluigimarudut
      @gianluigimarudut 2 месяца назад

      ​@@QuantitySurveyingStudio So, if the Contractor have VALID variations and the Engineer/Employer acknowledges it, the Contractor does not need to submit Claim Notices?

  • @wahiddawar7113
    @wahiddawar7113 2 года назад +1

    Very useful 👍 appreciate

  • @rajvlogs3926
    @rajvlogs3926 2 года назад +1

    Clearly understand thank you

  • @sabirmazari8761
    @sabirmazari8761 Год назад +1

    Good lecture Sir

  • @saddhaS
    @saddhaS Год назад +1

    Good one, simple

  • @bayan6325
    @bayan6325 2 года назад +1

    Amazing channel 👏 👌

  • @selamawitamanuel73
    @selamawitamanuel73 8 месяцев назад +1

    Clear 👍👍

  • @johnsonjoseph3377
    @johnsonjoseph3377 2 года назад +1

    Nice presentation

  • @irzathmohamed3151
    @irzathmohamed3151 Год назад +1

    Best video bro❤

  • @zulqarnainsatti6417
    @zulqarnainsatti6417 2 года назад +1

    Thanks for video. My question on which I need your insight is that if BOQ quantities differs for excavation and backfill works differ a lot and Contractor didn’t notice at the time of tendering but when contract awarded and work on site started so contractor mer with this unforeseen huge increase in quantity due to cut and fill. So now contractor is submitting his quantities based on real work executed let’s say 2 million m3 and BOQ quantities or contract quantities was 1 million m3 so what would the claim for this case. Thanks in advance

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  2 года назад

      It will be a variation.

    • @alvinsihombing18
      @alvinsihombing18 2 месяца назад

      @zulqarnainsatti6417: In brief, it will be variations (additional works/increased quantities).

  • @shyammohandas6293
    @shyammohandas6293 2 года назад

    If its an additional scope of works such as construction of an ancillary building to the adjacent plot,will it be considered as a variation or claim?

  • @mohamedhaneefaashrafali
    @mohamedhaneefaashrafali 2 года назад +1

    What about damage items by others…

  • @mohamedzafar9340
    @mohamedzafar9340 2 года назад

    Does Additional work and claim are same? Because the term“Claim” we used for all the payment request purposes

  • @teshanrathnayake6122
    @teshanrathnayake6122 3 месяца назад +1

    ❤Best

  • @knowledgeistospread1934
    @knowledgeistospread1934 2 года назад +1

    why you dont post any more jobs in your linked in job page?

  • @sameeraummer5112
    @sameeraummer5112 2 года назад +1

    Any format for submission

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  2 года назад

      Depends on companies and clients.

    • @gianluigimarudut
      @gianluigimarudut 2 месяца назад

      @sameeraummer5112: Follow your Company's standard templates. If needed, you can also adopt and modify templates from your previous companies or other sources.

  • @knowledgeistospread1934
    @knowledgeistospread1934 2 года назад +1

    can you do a video about cost report please

  • @haripriya2495
    @haripriya2495 9 месяцев назад

    Need software