Formula for damage as per 10.3 = 0.05% X number of delay days X ( Contract Price - Achieve Payment _on date from milestone) Doubt= if eot is grants for some days new milestone will create in this senerio what be the day from we imposed the damages 2. Price is total contract price or the (Contractor Price - IPC price from which damage start) If you know kindly write in comment
very nice
Thank you 😊💜
Sir what is the process to recover a payment from contractor
Formula for damage as per 10.3 = 0.05% X number of delay days X ( Contract Price - Achieve Payment _on date from milestone)
Doubt= if eot is grants for some days new milestone will create in this senerio what be the day from we imposed the damages
2. Price is total contract price or the (Contractor Price - IPC price from which damage start)
If you know kindly write in comment