Baharampur bypass along NH-34 (new NH-12) | Construction status | October 2019

Поделиться
HTML-код
  • Опубликовано: 1 ноя 2019
  • The current status of under-construction Baharampur (Berhampore) bypass along NH-12 (old NH-34) in West Bengal. The work was stalled since 2014. The videos are taken during August October 2019

Комментарии • 47

  • @dibyendubose2314
    @dibyendubose2314 2 года назад +2

    Dear Mr Hossain
    Is it possible to get an update on this portion from you.? Has the work on the new bridge over the Ganga restarted? Also what’s the status of the new bridge in Farakka which is supposed to take the load off the old barrage bridge. Would love to have an update from you…..no one else can match the finesse and the correctness of your updates.

    • @GolamMHossain
      @GolamMHossain  2 года назад +1

      Thankfully, the widening work has re-started for Baharampur bypass, including the work of new 4-laned Hooghly river bridge from last month (Dec 2021). The work is in full swing now.
      For the new 4-laned bridge at Farakka, the work is going to restart soon on-the-ground (officially, the work has already resumed, after the clearance of an independent review of the design and drawing. You may know that there was an accident at the construction site in Feb 2020 which halted the work and the whole bridge design was sent for a review. )

    • @dibyendubose2314
      @dibyendubose2314 2 года назад

      @@GolamMHossain
      Many thanks Mr Hossain for your reply. Somehow your reply got embedded beneath other mails and I had missed it. Good to know that work on both the bridges have started. I only wish that they had planned a 3+3 lane bridge (once and for all) in Farakka over the Ganga as is done on many other bridges for obvious reasons.

  • @skaftabalam8428
    @skaftabalam8428 3 года назад +1

    nice quality video ..thanks for update

  • @malaysarkar.6018
    @malaysarkar.6018 2 года назад +1

    The status is same in October,2021 also.

  • @skaftabalam8428
    @skaftabalam8428 3 года назад +1

    bg sound is best

  • @MistarulSk-qs6xt
    @MistarulSk-qs6xt 4 года назад +3

    এ-ই উড়ালপথটা হয়ে গেলে আমাদের খুবই ভালো হবে আর কয় বছর লাগবে?

    • @GolamMHossain
      @GolamMHossain  4 года назад

      একদম। এটা সবার জন্যে ই ভালো হবে। তবে NHAI একটু কড়া পদক্ষেপ না নিলে, ঠিকাদার এখন যেভাবে কাজ করছে তাতে অনেক দিন সময় লাগবে।

  • @TheBanibrata
    @TheBanibrata 4 года назад +3

    Thanks Golamda for sharing. So the status is exactly as we find in Google Map. BTW in apple map I can see the Dalkhola Bypass stretch is visible, and some progress at the western side of railway track also.

    • @sharathtummala5913
      @sharathtummala5913 4 года назад +1

      NHAI/ HCC main priority right now is Berhampore-Farakka Non-bypass completion by Jan-2020 and Farakka-Aradphur stretch by May-2020. Berhampore bypass works will move at snails pace barring bhagirathi major bridge.

    • @sharathtummala5913
      @sharathtummala5913 4 года назад +4

      Ahiron new bridge will be open before November end then old bridge will be repaired. Ballalpur ROB is also doable, structure fully done just the approaches is around 2 months work.
      Malda bypass only RHS side will be opened completely in two weeks time. Aradpur VUP nd Malda LHS also doable in 3-4 months but Kaliachak-Sujapur is bit difficult, lot of road work including culverts. Let's hope for the best.

    • @sharathtummala5913
      @sharathtummala5913 4 года назад +2

      Ahiron new bridge opened for traffic yesterday (18.02.20)

    • @GolamMHossain
      @GolamMHossain  4 года назад

      @Banibrata Patra Yeah, more or less, Baharampur bypass has the same status as you see in Google Maps. Nevertheless, there has been some progress in last few months. Now that the monsoon is over, we may see some visible change. Anyway, let's hope for the best.

    • @GolamMHossain
      @GolamMHossain  4 года назад

      @Sharath Tummala Thanks for such a precise update. Given the current financial situations, do you consider whether HCC will be able to meet even above targets (Kaliachak-Sujapur+Malda bypass+Aradpur overpass+Ahiron bridge + Ballalpur ROB) within the time frame that you have mentioned? Thanks in advance!

  • @bishnupurmobile4819
    @bishnupurmobile4819 4 года назад +2

    What is the end Date

    • @GolamMHossain
      @GolamMHossain  4 года назад

      It's running way behind schedule. Not sure, when they will complete it. If they want then it can be completed in a year but not much work is being done now.

  • @bananibiswas3846
    @bananibiswas3846 4 года назад +2

    Dada bortoman ki obostha?

  • @MistarulSk-qs6xt
    @MistarulSk-qs6xt 4 года назад +2

    ,দ্রুত নির্মান করবার জন্য ব্যবসথা নিন

  • @skaftabalam8428
    @skaftabalam8428 3 года назад +1

    sound like godfather movie

  • @silentsolitude2000
    @silentsolitude2000 2 года назад +1

    Bypass tar construction update in September 2021 aache??...

    • @GolamMHossain
      @GolamMHossain  2 года назад +1

      Kaj abar shuru hochche. HCC er funding je problem chilo seta koek mas age solve hoye geche.

  • @dasarathdhara3055
    @dasarathdhara3055 Год назад +1

    Dada NH16A update dao

  • @r.k.adventure1751
    @r.k.adventure1751 4 года назад +2

    Very nice creation

  • @tuhinakhatun9579
    @tuhinakhatun9579 2 года назад +1

    Beldanga to krishnonagar chapra koto k.mitar

    • @GolamMHossain
      @GolamMHossain  2 года назад

      Krishnanagar shorhor diye gele prai 90 km er moto.

  • @ramenghosh1085
    @ramenghosh1085 4 года назад +2

    Beharampur bypass at current status ki acha kaj ki cholcha

    • @GolamMHossain
      @GolamMHossain  4 года назад

      Lock down er age kaj cholchilo, tabe khub dhire.

  • @BiswajitDas-ml5tb
    @BiswajitDas-ml5tb 2 года назад +1

    thanks... any update in 2022

    • @GolamMHossain
      @GolamMHossain  2 года назад +1

      Yes, the work has resumed in full strength now. It is expected to be completed by end of 2023.

  • @sagnikbiswas1778
    @sagnikbiswas1778 4 года назад +2

    Current update kobe aasbe?

    • @GolamMHossain
      @GolamMHossain  4 года назад

      Ekhon to lockdown cholche! Tachara somosto construction work prai bondho. Phole agami koek mash kaj egobe bole mone hocchena!

  • @sagnikbiswas1778
    @sagnikbiswas1778 4 года назад +2

    Jokhon suru hobe tokhon deben

  • @sidhughosh6469
    @sidhughosh6469 3 года назад +2

    Ata complete hote hote ami more jabo 😭😭

    • @GolamMHossain
      @GolamMHossain  3 года назад

      Tai to mone hochhe. HCC eta ke jhuliye rekheche je ekhon oder kache fund nei.

  • @musaubirh
    @musaubirh 3 года назад +1

    Has the work started now in June 2021?

    • @GolamMHossain
      @GolamMHossain  3 года назад

      The work should start now as the funding issues are resolved. However, I didn't see much activity in April first week and I don't have any recent update.

  • @sagnikbiswas1778
    @sagnikbiswas1778 4 года назад +2

    After lockdown plz give some updates regarding this