E3: Paano mag estimate ng CEMENT, SAND, GRAVEL para sa CONCRETING Works ko?

Поделиться
HTML-код
  • Опубликовано: 21 окт 2024
  • 🏡 EPISODE 3:
    ⚡️ Sa video na ito, matututunan natin kung paano mag estimate kung ilang cemento, buhangin at graba ang kailangan natin para sa ating #Concreting #Works tulad ng #footing #columns #beams #slab
    #estimate #materialestimate #pinoykonstructideas #civilengineering #students #concrete #cement #gravel #sand #housecontruction
    #concretemix #concretemixratio
    Please like this video and SUBSCRIBED!
    Please Like and Follow our Facebook Page; / pinoykonstructideas

Комментарии • 24

  • @anthonybenitez673
    @anthonybenitez673 Год назад

    very informative my idol engr.

  • @konseptodesigns603
    @konseptodesigns603 4 года назад +1

    Very informative po nung contents niyo. Thank you.

  • @kathytimbal8835
    @kathytimbal8835 4 года назад +1

    Dami ko natututunan dito. Thank you.

  • @tommacabulostoledo
    @tommacabulostoledo 3 года назад +1

    Ayos! God bless us all!

  • @jesonrepana3197
    @jesonrepana3197 2 года назад

    Pwede ka po ba mag order ng 12.51cu.m na buhangin?

  • @tommacabulostoledo
    @tommacabulostoledo 3 года назад +1

    Comment ko lang ulit yung quantity ng water.

    • @pinoycivilengineerkonstruc3515
      @pinoycivilengineerkonstruc3515  3 года назад

      may mga new episodes po ,,
      EP6: Four Storey Column Rebar Cutting List with Splicing (Lapping Length, Lapping Zone)
      ruclips.net/video/4MW9DtVD9uw/видео.html

  • @jersoncarisosa5983
    @jersoncarisosa5983 3 года назад +1

    Sir..kong mag buhos ka ng 0.36 cubic meters ng footing kong yung estimate mo ang gagamitin..kakapal yung footing mo..aabot ng 0.6508 after fooring...paano yan yung actual dimension ng footing mo hindi yung nasa actual plan..

    • @pinoycivilengineerkonstruc3515
      @pinoycivilengineerkonstruc3515  3 года назад

      Hello sir, ung sinasabi po ba ninyo sir is ung nag round off ako ng cement bags from 3.24 bags to 4 bags?
      Sa estimate po, nag round off po tayo para pag mag order tayo ng cement bags is whole number tayo.
      But sa actual dun tayo sa estimate mag base po.

    • @pinoycivilengineerkonstruc3515
      @pinoycivilengineerkonstruc3515  3 года назад

      EP7: Four Storey Beam Rebar Cutting List with Splicing (Lapping Length, Lapping Zone)
      ruclips.net/video/Blsgx0IKL1c/видео.html

    • @pinoycivilengineerkonstruc3515
      @pinoycivilengineerkonstruc3515  3 года назад

      may mga new episodes po ,,
      EP6: Four Storey Column Rebar Cutting List with Splicing (Lapping Length, Lapping Zone)
      ruclips.net/video/4MW9DtVD9uw/видео.html

  • @ellebrianonofre4117
    @ellebrianonofre4117 3 года назад +1

    Pwede pong hingin yung excel?

    • @pinoycivilengineerkonstruc3515
      @pinoycivilengineerkonstruc3515  3 года назад

      EP7: Four Storey Beam Rebar Cutting List with Splicing (Lapping Length, Lapping Zone)
      ruclips.net/video/Blsgx0IKL1c/видео.html

    • @pinoycivilengineerkonstruc3515
      @pinoycivilengineerkonstruc3515  3 года назад

      may mga new episodes po ,,
      EP6: Four Storey Column Rebar Cutting List with Splicing (Lapping Length, Lapping Zone)
      ruclips.net/video/4MW9DtVD9uw/видео.html

  • @gomercorales8072
    @gomercorales8072 3 года назад

    Other method - design mix