In this video, you will look at an example to calculate lead times using Bill of materials. #BOM #BOMFundas #leadtimes #typesofBOM #billofmaterial #productdesign #inventoryitems
Hi I have question : For manufacturing/assembling of one component of X it is required one week lead time .if we plan the availability of all components in 9th week. In one week how 100 -X components will be assembled?
Very Good video sir, Thank you very much!
Thank you so much. Your VDO is so useful.
Thankyou 👍
Thank you so much
Hi I have question : For manufacturing/assembling of one component of X it is required one week lead time .if we plan the availability of all components in 9th week. In one week how 100 -X components will be assembled?
same question, X should be in 9th week