Hello Nurmaya, the standard efficiency of the cyclone preheater is below 10%, meaning that the less dust particles that come out of the preheater system, the better.
Hello Siti. Thank you for your attention. Sorry, are you still in college or already working in a cement factory? To calculate the preheater system specifications it is related to the design, and there are several designs of cyclone preheater, there are 4 cyclone levels, 5 cyclone levels and 6 cyclone levels, according to the clinker production capacity. Meanwhile, I am not in a position as a designer cement factory, but I am in a position to operate and how ton optimize the operation of a cement factory.
Material feed into the preheater system depends on the clinker production capacity. For a clinker production capacity of 8000 tonnes per day, the material fed to the preheater is around 550 tonnes per hour. And for a clinker production capacity of 11,000 tons per day, the material fed to the preheater is around 750 tons per hour.
Good information guru ji sir
Thank you for the comments, I hope this video is useful for you sir...🙏
Thanks for your efforts.
Thank you for your attention, sir, hopefully it will add a little knowledge and be useful.
helo sir, thank you for good information. I want to ask, what is the standard efficiency of the suspension preheater??
Hello Nurmaya, the standard efficiency of the cyclone preheater is below 10%, meaning that the less dust particles that come out of the preheater system, the better.
Helo sir, thank you for good information. I want to ask, how to calculate suspension preheater specifications?
Hello Siti. Thank you for your attention.
Sorry, are you still in college or already working in a cement factory?
To calculate the preheater system specifications it is related to the design, and there are several designs of cyclone preheater, there are 4 cyclone levels, 5 cyclone levels and 6 cyclone levels, according to the clinker production capacity. Meanwhile, I am not in a position as a designer cement factory, but I am in a position to operate and how ton optimize the operation of a cement factory.
Great Videos
Good information ji sir tq so much for giving this information
May I know how large or small the meal is entering in the pre-heater system?
Material feed into the preheater system depends on the clinker production capacity.
For a clinker production capacity of 8000 tonnes per day, the material fed to the preheater is around 550 tonnes per hour.
And for a clinker production capacity of 11,000 tons per day, the material fed to the preheater is around 750 tons per hour.
Thanks