Thank you sir for your knowledge sharing.you r explained the task list in a very detailed manner. can you upload the video of how to do maintenance plan.. i am learning SAP PM fucntional module by own through the RUclips video. really very useful for me.. thanks a lot
Hello Amit! Today, I have many maintenance plans for a specific equipment. Each maintenance plan has many items, that are inside a word document. The problem is, when I want to change an item that is in the first maintenance plan, I have to enter on each further maintenance plan's document and change it manually. Like you choose the period that a maintenance plan will be launched for the execution, I would like to have a task list, and choose the period that a specific item will correspond to the maintenance plan. Example: 1W 1M 6M 10. Replace the oil filter X X 20. Replace the oil X 30. Clean the air filter X X X And after that, when a monthly maintenance plan launches to be executed, SAP would compile the items 10 and 30 to a word document, and then display it for me to print and send it to the maintenance team. Is that possible? Thank you very much
Thanks for the video. How do we trigger the Task list Configuration for PM orders from Fiori?... Do we need to be in SAPGUI if we want this functionality?...
Thank you sir for your knowledge sharing.you r explained the task list in a very detailed manner. can you upload the video of how to do maintenance plan.. i am learning SAP PM fucntional module by own through the RUclips video. really very useful for me.. thanks a lot
hi can u plz share the link
Very good brother we are currently friend 👍
excellent presentation … shows your experience! Thanks for sharing this
My pleasure!
@@AmitAhiniya sir pls help with S4 hana pm configuration
Hello Amit!
Today, I have many maintenance plans for a specific equipment. Each maintenance plan has many items, that are inside a word document. The problem is, when I want to change an item that is in the first maintenance plan, I have to enter on each further maintenance plan's document and change it manually.
Like you choose the period that a maintenance plan will be launched for the execution, I would like to have a task list, and choose the period that a specific item will correspond to the maintenance plan.
Example:
1W 1M 6M
10. Replace the oil filter X X
20. Replace the oil X
30. Clean the air filter X X X
And after that, when a monthly maintenance plan launches to be executed, SAP would compile the items 10 and 30 to a word document, and then display it for me to print and send it to the maintenance team.
Is that possible?
Thank you very much
Thanks for the video. How do we trigger the Task list Configuration for PM orders from Fiori?... Do we need to be in SAPGUI if we want this functionality?...
How to use Relationship in public cloud?
which software is required
SAP any version.
Sir can u plz help me I have to study asrs system at crm and collect the failure data and develope the sap pm tasklist.
@@shobhangiverma706 Pl share your contact details.
Hi
Not proper display