Erection Sequence of Vertical & Horizontal Precast Elements |Installation Methodology |

Поделиться
HTML-код
  • Опубликовано: 6 сен 2024
  • 1. Prepare the permit and Safety documents
    2. Approved and sufficient capacity of mobile/crawler crane is usr
    3.Lifting area is fully barricaded and signboard placed
    4.precast vehicle movement will be controlled by a banks man or flag man
    5.Truck is placed near the crane
    6.Lifting supervisor or rigger inspect load lifting gear lifting point proor to start
    7.Tagline is attached to the elements for controlling movements
    8.Precast element is moved to designated position
    9. panel adjusted to correct position and secure with props
    10. Alignment and verticality of panel
    11.finall stability of props by supervisor or formam