CALCULATION OF CEMENT SAND AND AGGREGATES FOR COLUMN
HTML-код
- Опубликовано: 17 мар 2019
- OTHER ESTIMATION VIDEOS
VIDEO 1
QUANTITY OF CEMENT AND SAND IN PLASTER
• CALCULATION OF NUMBER ...
VIDEO 2
CALCULATION OF BRICKS CEMENT AND SAND
• CALCULATION OF NUMBER ...
VIDEO3
CALCULATION OF CEMENT SAND AND AGGREGATES IN CNCRETE
• QUANTITY OF CEMENT, SA...
#CIVILENGINEERING #STEEL #ESTIMATION
Subscribe to my vlogging channel FBH Vlogs here
/ @fbhvlogs271
Join me on telegram
t.me/joinchat/AAAAAE_3K35dp8c...
Follow me on instagram
pB0UngpDFY...
Follow our facebook page
/ civilenineeringworldwide Наука
Simple Superb Sir 👍
Thank you🙏
Bohat acha se aapne bataya video thanks sir
Very nice informetion
Nice bro ....very informative video 👍
Outstanding sir
Very helpful
Thank u sir . Thank u so much sir
Nice
Great information sir❤🌹👍🍫
Thanks
Bohot achha tarika tha Aapka samjhane Ka👏mujhe aapki video Pasand aayi, aur sir ye batao 1.54 kaise Aaya
1:3:3
Cement :sand:aggregate milakar column casting kiya hain for 2storey building is it ok or unsafe?Column size 10inch sure, distance 12foot
Thank you so much Brother it is very useful and easy to understand thank you so much❤️🙏🏻
thankyou sir
Thanks sir
Nyc...
👍👍
Thanks sir.lekin hamko bataiye 5 bori cement lagega balu to choriye .agrigates kitna bartan lagega bataiye .samjh nahi Aya.
Thank you sir ji....
Y r u multiple the 35.315 in sand and courses aggregate
good
Aoa rcc colum ka complete material Dana foot m
पुरी तरह कैल्कुलेशन करके बताये भाईजी
or agar sand or aggregate ko bhi kg me nikalna ho to?
Sir ji.....steel ka volume deduct kyu nhi kiya .....
Sir,
How is 54% is calculated as 1.54 x 0.0552?
Your explanation would be greatly appreciated.
Thank you
dry volume is much more than wet volume. the 0.552 is a wet volume, dry volume is 54% more than wet so multiply 0.552 by 1.54. or you can do 0.552*(1+0.54), same thing.
Sir CFT ki kg se kese lekale
Thanks ✌👌
Concurred me 54% day volum hote he but 1.54% keshe yaya sir
You are
m20 stand for???
Indian standard code for building RCC structure.
Sir,
How 54% is calculated as 1.54 ?
Bhai 54% increase krky lety h
100% for wet and 54%dry cond
Then
100+54=154/100=1.54
Unchai feet ke hisab se batate to sajh aata. Zameen ke ander 3feet upar 10feet aisa samjhate to sajh aata.
Jinab gachi kashur ason
1450/1440 kg /
Density of cement 1440kg/M3
Sand 1450kg/m3
Y 1.54? It should be 0.54?