A worker completes a job in a certain number of hours. The standard time allou for the job is 10 hours, and hourly rate of wages is Re. 1. The worker earns at th 50% rate a bonus of Rs. 2 under Halsey Plan. Ascertain his total wages under the Rowan Premium Plan. Indha sum explains panunga
Halsey plan: Rs 270
Barth: Rs 268.32
Labour cost per hour:
Under Halsey: rs 13.5
Under Barth v rs 13.416
Mam😘🥰😙.... really🤗 ur teaching is easily understand to lower students ... 🥰😇
Halsey plan --13.5. and. barth scheme -- 13.4
Tqq so much mam❤
A worker completes a job in a certain number of hours. The standard time allou for the job is 10 hours, and hourly rate of wages is Re. 1. The worker earns at th 50% rate a bonus of Rs. 2 under Halsey Plan. Ascertain his total wages under the Rowan Premium Plan.
Indha sum explains panunga
Mam Halsey plan = 270
Bairth variable plan = 268.3
Mam ans crta mam
Labour cost find panaliya ma..
Labour cost Earnings/time taken
270/20 =13.5
268.3/20= 13.415
Ans crtnga mam
Gud
1. 13.5
2. 1.34
1*√72*60 =65.7? Plz explain
Same dout
Halsey plan 270
Barth plan 268.32 or 268.3
Cost per labour
A.1.5
B.13.416 or 13.415 correct mam
Gud