CAVITE-LAGUNA EXPRESSWAY (CALAX) PROJECT
Project Description:
The project is a 44.58 km. four (4)-lane closed-system tolled expressway connecting CAVITEX and SLEX. The project will start from the CAVITEX in Kawit, Cavite and end at the SLEX-Mamplasan Interchange in Biñan, Laguna. The project will have the following subsections:
Project Subsections
Length
(km)
1
Cavitex Connection to Open Canal Interchange
8.68
2
Open Canal Interchange to Governor’s Drive Interchange
9.86
3
Governor’s Drive Interchange to Silang (Aguinaldo) Interchange
8.64
4
Silang (Aguinaldo) Interchange to Silang East Interchange
3.16
5
Silang East Interchange to Sta. Rosa-Tagaytay Interchange
5.14
6
Sta. Rosa-Tagaytay Interchange to Laguna Boulevard Interchange
2.34
7
Laguna Boulevard Interchange to Laguna Technopark Interchange
3.30
8
Laguna Technopark Interchange to Mamplasan Toll Barrier
3.46
PPP Scheme: Solicited Project, Build-Transfer-Operate
-Private sector to finance, construct, operate and maintain the entire expressway
Concession Period: 35 years (including 5 years design and construction)
Start of Concession Period: July 10, 2015 (TCA Signing Date)
Right of Way:
60 meters, except for Laguna Techno Park & Laguna Boulevard (40 meters), and Greenfield Development Corporation (50 meters).
Interchanges:
8 interchanges and 1 toll barrierr
Bridges:
3,575 meters inclusive of 444 meters of viaduct
Project Objectives:
This project aims to:
Support national development policy and provide efficient transport facilities for the Eco-zones in Cavite and Laguna.
Reduce traffic congestion particularly in Governor’s Drive, Aguinaldo Highway and Sta. Rosa-Tagaytay Road which are heavily congested.
Improve competitiveness of Region IV-A/CALABARZON as an investment destination.
Project Benefits:
At the end of construction, the project is expected to:
Reduce travel time from CAVITEX (Kawit) to SLEX (Mamplasan Interchange in Biñan, Laguna) from 2 hours to 35 minutes (70% reduction).
Project Concessionaire:
MPCALA Holdings Inc.
Project Cost:
Activities
Amount (Billion)
Civil Works
P 25.425
Right-of-Way
P 10.201
Independent Consultant (50%)
P 0.112
Total
P 35.738
Project Status:
· Right-of-Way Acquisition (ROWA) accomplishment (actual site possession)
Ø Laguna Side : 100.00%
Ø Cavite Side : 74.40%
· Subsections 8, 7 and 6 (Sta. Rosa to Mamplasan) were partially opened to traffic on October 30, 2019.
· Toll Operation Permit (TOP) was issued last February 7, 2020 for Subsections 8, 7 and 6.
· Toll Operation Permit (TOP) was issued last June 18, 2021 for Subsection 5.
· Subsection 5 (Sta. Rosa to Silang East IC) was open to traffic last August 24, 2021.
· Contractor for Cavite Segment Subsection 1 already mobilized.
· Interim Permit to Operate was issued last November 6, 2023 for Subsection 4.
· Subsection 4 (Silang East IC to Silang Aguinaldo IC) was open to traffic last November 8, 2023.
· Toll Operation Permit (TOP) was issued last January 22, 2024 for Subsection 4.
Project Alignment:

Project Timeline:
Segment
Start Date
Completion Date
Remarks
Laguna Segment
100.00%
Subsection 8
July 2017
October 2019
100%
Subsection 7
July 2017
October 2019
100%
Subsection 6
September 2018
October 2019
100%
Subsection 5
September 2018
August 2021
100%
Subsection 4
March 2021
December 2023
100.00%
Cavite Segment
12.59%
Subsection 3
July 2019
December 2024
7.90%
Subsection 2
July 2019
June 2025
11.32%
Subsection 1
July 2019
May 2025
17.05%
Overall accomplishment: 60.00%
Aba ang ganda sa aerial view,,,nice update my friend
Thank you boss
23like very nice friend
Thank you very much
Thank you for sharing the wonderful video.
Welcome boss,thank you for watching..
Ayos lods alignment update sa lugar na yan maganda na kalsada. Ok talaga ang ganito mga magandang plano development mga bagong kalsada o pagpapaganda ng daan. Ayos. StayKonek po lods Kitakits. Keep safe.
Yes po salamat po ng marami sa laging pagsubaybay..
Sobrang ganda na po tlga bungga bunggah hinihingal ka idol
Ha ha oo nga po bigat kc ng motor ko ha ha,salamat po
Hahaha. Good to having us back my good Ladz. It's been a while since the last time I've watched one of my favorite bloggers. There you go my friend with latest updates. Correct me if I'm wrong. I've heard that there will be a plan for LRT6 in CAVITE. God bless
Yes Doc welcome back po he he thats been awhile po yes po plano po diumano going to tagaytay at balita po natin e sa Aguinaldo hiway po cya dadaan..salamat po,magandang araw po
Boss jan sa tinambayan mo jan kme sa hapon madalas kumain ng Pares mahangin jan sayang di kta sa Aerial shot ung Subd.nmin Bostos Heights s gilid kc nmin dadaan ung Calax palabas na ng Kawit
Ah ganun po ba boss lapit nyo lng po pala dyan he he,di bale may next time pa nman po he he,salamat po
New subscriber po,pa shout out😊
Salamat po tukayo next vlog po God willing..