CAVITE-LAGUNA EXPRESSWAY (CALAX) PROJECT
Project Description:
The project is a 44.58 km. four (4)-lane closed-system tolled expressway connecting CAVITEX and SLEX. The project will start from the CAVITEX in Kawit, Cavite and end at the SLEX-Mamplasan Interchange in Biñan, Laguna. The project will have the following subsections:
Project Subsections
Length
(km)
1
Cavitex Connection to Open Canal Interchange
8.68
2
Open Canal Interchange to Governor’s Drive Interchange
9.86
3
Governor’s Drive Interchange to Silang (Aguinaldo) Interchange
8.64
4
Silang (Aguinaldo) Interchange to Silang East Interchange
3.16
5
Silang East Interchange to Sta. Rosa-Tagaytay Interchange
5.14
6
Sta. Rosa-Tagaytay Interchange to Laguna Boulevard Interchange
2.34
7
Laguna Boulevard Interchange to Laguna Technopark Interchange
3.30
8
Laguna Technopark Interchange to Mamplasan Toll Barrier
3.46
PPP Scheme: Solicited Project, Build-Transfer-Operate
-Private sector to finance, construct, operate and maintain the entire expressway
Concession Period: 35 years (including 5 years design and construction)
Start of Concession Period: July 10, 2015 (TCA Signing Date)
Right of Way:
60 meters, except for Laguna Techno Park & Laguna Boulevard (40 meters), and Greenfield Development Corporation (50 meters).
Interchanges:
8 interchanges and 1 toll barrierr
Bridges:
3,575 meters inclusive of 444 meters of viaduct
Project Objectives:
This project aims to:
Support national development policy and provide efficient transport facilities for the Eco-zones in Cavite and Laguna.
Reduce traffic congestion particularly in Governor’s Drive, Aguinaldo Highway and Sta. Rosa-Tagaytay Road which are heavily congested.
Improve competitiveness of Region IV-A/CALABARZON as an investment destination.
Project Benefits:
At the end of construction, the project is expected to:
Reduce travel time from CAVITEX (Kawit) to SLEX (Mamplasan Interchange in Biñan, Laguna) from 2 hours to 35 minutes (70% reduction).
Project Concessionaire:
MPCALA Holdings Inc.
Project Cost:
Activities
Amount (Billion)
Civil Works
P 25.425
Right-of-Way
P 10.201
Independent Consultant (50%)
P 0.112
Total
P 35.738
Project Status:
· Right-of-Way Acquisition (ROWA) accomplishment (actual site possession)
Ø Laguna Side : 100.00%
Ø Cavite Side : 74.40%
· Subsections 8, 7 and 6 (Sta. Rosa to Mamplasan) were partially opened to traffic on October 30, 2019.
· Toll Operation Permit (TOP) was issued last February 7, 2020 for Subsections 8, 7 and 6.
· Toll Operation Permit (TOP) was issued last June 18, 2021 for Subsection 5.
· Subsection 5 (Sta. Rosa to Silang East IC) was open to traffic last August 24, 2021.
· Contractor for Cavite Segment Subsection 1 already mobilized.
· Interim Permit to Operate was issued last November 6, 2023 for Subsection 4.
· Subsection 4 (Silang East IC to Silang Aguinaldo IC) was open to traffic last November 8, 2023.
· Toll Operation Permit (TOP) was issued last January 22, 2024 for Subsection 4.
Project Alignment:

Project Timeline:
Segment
Start Date
Completion Date
Remarks
Laguna Segment
100.00%
Subsection 8
July 2017
October 2019
100%
Subsection 7
July 2017
October 2019
100%
Subsection 6
September 2018
October 2019
100%
Subsection 5
September 2018
August 2021
100%
Subsection 4
March 2021
December 2023
100.00%
Cavite Segment
12.59%
Subsection 3
July 2019
December 2024
7.90%
Subsection 2
July 2019
June 2025
11.32%
Subsection 1
July 2019
May 2025
17.05%
Overall accomplishment: 60.00%
Enjoy your wonderful tour, wishing you stay Happy and Healthy my dear friend ❤❤❤👍
Yes po thank you for watching..
Magandang araw uli sir ayan na, na gawana ang lawak pala dyan
Good day po
Maam,opo maraming salamat po
Thanks for sharing boss
Thanks for watching boss
ride safe sir
Thank you boss
maganda po yan pag mabuksan ngayon taon
Opo.maam laking tulong po,salamat po
💪💪💪
Thank you for watching sir
Yes this year na Governor's Drive! Sana totoo
Hopefuly sir Jun laking tulong po talaga yan,salamat po maganfang gabi po
Salamat Sir sa Update.kelan kaya uumpishan un tunnel sa aguinaldo highway
Wala po tayong balita sir di bale po every month may update po tayo dyan sir kaya masusubaybayan po natin yan,salamat po
Sana mag kaayos na yan sa may likod ng bahay na blue para umusad na yan nag papa delay jan eh
May nakausap po tayo dyan,hindi pa raw po cpa nbabayaran bka kaya po may delay,,magandang gabi po
Salamat sa update however everything that you’ve been showing are the street you’re traveling with and nothing about the project development..
Good day po sir Lito,I just want to show how to go to the construction site kaya po pati mga daan isinasama po natin sa video,anyway salamat po
@@alexberuelavlog20 ,, yap too much abt the road leading to the project, talk about the project and not the road leading to it,, the road can be check from the travel apps,, people would be more interested on the project status than where your traveling too.
Thank for your concern sir Lito,improve po natin next time,,salamat
Mdyo matatagalan pa ata malaking area pa ang hindi pa gawa.
Balita po e this year daw po boss,but lets wait amd see po,salamat po