Long Wall and Short Wall Method (Concept + Numerical) | Civil Engineering | GATE 2021
HTML-код
- Опубликовано: 6 сен 2024
- Long Wall and Short Wall Method (Concept + Numerical) | Civil Engineering | GATE 2021
#GATE2021 #Adda247CivilEngineering #EngineerAdda
Month End Super Sale!
Give Wings To your Preparation!
Flat 30% Off On All Study Material
+ 5% Off on App*
Use Code - BUMPER
Mahapacks | Live Classes | Test Series | Video Courses | Ebooks
Buy Now - bit.ly/3aHnVg3
Get PDF:-bit.ly/3aGiw8R
Best Book For Engineers Exams Preparation: store.adda247....
Preparing for SSC Exams, Get a Free Counselling-
Click Here:: bit.ly/37o6wHN
Preparing for Engineering Exams, Get a Free Counselling - Give a Missed call on 011 41183264
Download Our App for Daily Quiz | Study Material: bit.ly/30bq8Mh
Subscribe Adda247 RUclips Channels for All Competitive Exams Preparation:
SSC Adda (SSC & Railway Exams Preparation): bit.ly/2lUAVvb
Bankers Adda (Bank Exams Preparation): bit.ly/2mjJ3FF
Engineers Adda (Engineering Exams Preparation): bit.ly/2kLTvoZA...
Teachers Adda (Teaching Exams Preparation): bit.ly/2kljaVf
Defence Adda (Defence Exams Preparation): bit.ly/34vxMmh
State Exams (State Exams Preparation): bit.ly/2EQcLYY
Adda247 Bengali (Exams Preparation in Bengali): bit.ly/2vCQJYt
Adda247 Marathi (Exams Preparation in Marathi): bit.ly/38oi5ih
Adda247 Tamil (Exams Preparation in Tamil): bit.ly/3aiWgSK
Adda247 Telugu (Exams Preparation in Telugu): bit.ly/38jcs52
SSC Adda247 Live Class Schedule with Playlist Links:
==Live Class Schedule with Playlist links::
DMRC JE | SSC JE | CIL MT
►9:00 AM - SSC JE Reasoning - bit.ly/2OqbfRp
►11:00 AM - DMRC JE | CIT MT Maths - bit.ly/33Zl9jF
►12:00 PM - DMRC JE English - bit.ly/2Ot0Kgy
►01:00 PM - SSC JE | CIL | General Science - bit.ly/37gHGdN
BARC | VIZAG STEEL | ISRO 2019 Exam
►2:30 PM - BARC | VIZAG STEEL | ISRO Electronics & Communication - bit.ly/2CRWj9v
JE Special
►7:00 PM - JE Civil Engineering - bit.ly/35Ni9r1
►8:00 PM - IS 456 Civil Engineering - bit.ly/2VHr2k6
SSC JE | VIZAG MT
►8:30 PM - ELECTRICALS - bit.ly/2Y8USxm
►8:30 PM - Mechanical - bit.ly/2L9GFL4
Follow us on Social Media-
⇒ Visit our SSCAdda website: bit.ly/2CidhNX
⇒ Check All Latest Govt Jobs 2020: bit.ly/3aaaqX9
⇒ Facebook Page: bit.ly/2PKGyJc
⇒ Twitter: bit.ly/2r12JRx
⇒ Instagram: bit.ly/2rMVMDF
⇒ Linkedin: bit.ly/2PcVP3H
⇒ Sharechat: bit.ly/33EoljO
⇒ Tiktok: bit.ly/2LiF06c
Our Products for All Government Exams Preparation:
SSC Exams Preparation Products: bit.ly/ssc-exams
Banking Exams Preparation Products: bit.ly/banking-...
Defence Exams Preparation Products: bit.ly/2IgFN5s
Teaching Exams Preparation Products: bit.ly/teaching...
Railway Exams Preparation Products: bit.ly/railway-...
Insurance Exams Preparation Products: bit.ly/insuranc...
#EngineerAdda
Hi Guys, Please Click On This Link To Get PDF:-bit.ly/3aGiw8R
Sir I'm unable to download file!
Total concrete work 5.19m3
Total brick work 3.104m3
Excavation 15.55m3
Total work =5.836m3
👌👌👌👌👌👌aap bohot accha explain krte h sir...itni asaani se kbhi ni hue mere se ye questions
Total quantity(Including Excavation,concrete,brickwirks and superstructure)=51.836m3
Total Brick work quantity(Foundation and superstructure)=31.104m3
Excellent session Sir Thank you
Total work =51.85 m3, total brick work = 31.11m3 total concrete work = 5.19 m3 , excavation= 15.55m3 thanks sir ,👌👌👌👌
Excavation work. - 15.55m^3. Total concrete work in foundation - 5.19 m^3. Total brick work in foundation, plinth and super structure 31.11m3. ( Total work )- 51.85m3
Total quantity =51.83m3
Total brick work ( substructure + super structure )=31.104m3
Total quantity (including excavation, concrete, brick work and superstructure) =51.836 Total brick work (foundation and superstructure) =31.104. B/w in substructure =10.95. B/w in superstructure =20.16. Thank u so much sir apke wajase mera daily improvement ho raha ha sir
Total work = 51.84 m3
Total Concrete work in foundation = 5.184 m3
Total BrickWork ( including Ist, IInd footing,plinth and superstructure) = 31.104 m3
Brickwork in Ist footing = 3.456 m3
Brickwork in 2nd footing = 2.88 m3
Brickwork in plinth = 4.608 m3
Brickwork in Superstructure = 20.16 m3
Earthwork in Excavation = 15.552 m3
Sorry Sir I couldn't come live but I solved it later by myself.
1 E/W in excavation 15.55 cu m
2 C/C in foundation 5.18 cu m
3 Brick work in foundation 10.95 cu m
4 Brick work in super structures 20.16 cu m
total work 51.84 cu m
brick work 31.11 cu m
Total Work - 51.834 m3
Brick Work - 31.104 m3
Total quality 51.91m³
B/w in substructure = 10.95m³
B/w in superstructure = 20.16m³
TOTAL B/W= 31.11M³
ruclips.net/video/jm7Rah3LxpM/видео.html
Estimation practically..
Are wah sir mja aa gya apka lacture dekh kr..♥👌
Total work done:-51.84 cum
Earthwork in foundation:-15.55 cum
Total concrete work:- 5.184cum
Total brick work:-31.11 cum
Earthwork =15.35m3
Concrete work =5.19 M3
Brick work = 30.54 M3
So total quantity = 51.09 M3
Sir ty u for teaching 👍👍👍
If you want to know how to make estimate practically then watch my channel
ruclips.net/video/jm7Rah3LxpM/видео.html
Sir brick work in foundation long wall ka 1.74 right hai
Sir aapke samjhane ke bad agar koi students nhi samajh pata hai to fir bahot dikkat hai qki aapke samjhane ki tarika hi unik hai sir aapke ek video se estimations pura samjha me lag gaya hme lng wall method and short wall method thank u so much sir 🙏🙏🙏
Bht accha lga sir dekh k❤❤❤....understood v well
BW=31.11m^3
TC=5.19m^3
TE=15.55m^3
Total work=51.85m^3
Waah
Earthwork= 15.55cum
Concrete= 5.19cum
Brickwork=31.10cum
Total quantity of work= 51.84cum.
Total work ( excavation , concrete , brickwork )= 51.83 m³ - Brick work 31.1 m³ - excavation = 15.5 m³ -- nd concrete = 5.184 m³
soil excavation 5.19cum
sub brick work 10.949m^3
super brick work 20.16m^3
total sub+ super brick work 31.109m^3
Total Excavation=15.55cum.
Total Concrete=5.19cum.
Total brick work=31.11cum.
Thank you so much sir. Very much productive session it was as I always have fear on this from clg days. Now it's pretty much clear to me. Thanks again.
Dhasu lecture 👍 each and every point clear 👌
Awesome explanation ❤️
Thank you sir for teaching this question btw love from himachal pradesh 😍😍😍😍
Thankyou sir your teaching method is super
Sir ji aap contrct and account ke specifition and valuation per lectures banao na plzz sir
Ty so much sir ☺️😍❣️
Sir iskii play list nh bani hai kyy?? Mil nhi rhe h iske agey k set?
good Work loved it !
Excellent session sir👌
mujhe koi ye btao bhai.. dhalaiya ka quantity nhi nukalenge kya???
Thank u so much sir
Thank you sor
Good afternoon
Sir quantity wala samjh nhi aya
Please sir help kariye🙏
hello sir
2
2.88
Long ka 1.74aa raha hai
Faltu.
2.88