Potain MCT 88 installation for NAZERO Constructions
HTML-код
- Опубликовано: 31 дек 2024
- Potain MCT 88 installation for NAZERO Constructions in Victoria Rd Manly.
Towers: 26 metres x 1.2 metres
Jib: 25 metres
Base P12 / concrete 30 NPA
The installation occurred across 2 days (over an 8 day period), which allowed 1 week for the concrete to cure, be strength tested & approved for crane installation.
Post installation our technical team commissioned the crane & hand it over to NAZERO to start their build on the heritage listed building in which they will keep the facade in tact & take the building a further 2 stories into the sky of Manly, providing uninterrupted views of the world famous surfing Mecca & clean line of sight to Sydney Harbour.