Potain MCT 88 installation for NAZERO Constructions

Поделиться
HTML-код
  • Опубликовано: 31 дек 2024
  • Potain MCT 88 installation for NAZERO Constructions in Victoria Rd Manly.
    Towers: 26 metres x 1.2 metres
    Jib: 25 metres
    Base P12 / concrete 30 NPA
    The installation occurred across 2 days (over an 8 day period), which allowed 1 week for the concrete to cure, be strength tested & approved for crane installation.
    Post installation our technical team commissioned the crane & hand it over to NAZERO to start their build on the heritage listed building in which they will keep the facade in tact & take the building a further 2 stories into the sky of Manly, providing uninterrupted views of the world famous surfing Mecca & clean line of sight to Sydney Harbour.

Комментарии •