Saket sir, I had a question regarding Velocity. If historical velocity of a scrum team is 30 and in one of the sprints, the team could not complete a 5 pointer story. What will be the velocity of that particular sprint?
Velocity of given sprint is Sum total of the story points completed (met DoD) in given sprint , it has not much to do what was the history of velocity.
hello sir can you help me for this question During planning, the team has used story points to estimate the user stories. One of the stories is estimated at 3 story points and took 6 days to complete. During the sprint, this story was fully developed, tested, and reached the done stage. At the sprint review, it was accepted by the product owner and the team successfully reflected the completion as part of their team velocity. How many points have they added to the velocity for this story? A:3 B:6 C:1 D:0
👍🏻 Good as always 💯
Saket sir, I had a question regarding Velocity. If historical velocity of a scrum team is 30 and in one of the sprints, the team could not complete a 5 pointer story.
What will be the velocity of that particular sprint?
Velocity of given sprint is Sum total of the story points completed (met DoD) in given sprint , it has not much to do what was the history of velocity.
hello sir can you help me for this question
During planning, the team has used story points to estimate the user stories. One of the stories is estimated at 3 story points and took 6 days to complete. During the sprint, this story was fully developed, tested, and reached the done stage. At the sprint review, it was accepted by the product owner and the team successfully reflected the completion as part of their team velocity. How many points have they added to the velocity for this story?
A:3
B:6
C:1
D:0
What is the confusion since its simple 3 pointer user story will add 3 points to Velocity