Project Management: Crashing a Project

Поделиться
HTML-код
  • Опубликовано: 23 ноя 2024

Комментарии • 81

  • @brittanykoskie9361
    @brittanykoskie9361 10 месяцев назад +9

    This went hand in hand with a homework problem I was struggling with. Thank you for your detailed explanation!

  • @zakiapayab7240
    @zakiapayab7240 10 месяцев назад +4

    I just watched this well explained video. Step by step solution to the end was very interesting.

  • @OrganicAlumination
    @OrganicAlumination Год назад +2

    I really need this because online classes and these charts and the DNA strand map .... I hate how lost I can be.

  • @cerenaltntas4546
    @cerenaltntas4546 10 месяцев назад +2

    Helal olsun kardeşim sana sayende dersi gecicem

  • @et4918
    @et4918 Год назад +6

    Thanks I cearly understand how to crashing a project. In fact, I think you teach better than my school's professer even English is not my mother tongue haha. Well teaching !!!!!

  • @adityabagayatkar1947
    @adityabagayatkar1947 7 месяцев назад +1

    Thank you for the explanation. Just One question. Why don't we crash A and E further ? we only consider A and E's crash week as 1

    • @The_Business_Doctor
      @The_Business_Doctor  5 месяцев назад

      A can be crashed by only 1 week (from 4 to 3). After that, there are two critical paths, so even if you crash E, you can't crash the path with A any more so you would be wasting your money to crash E.

  • @ranjanghosh4321
    @ranjanghosh4321 Год назад

    Its very well defined. One question. While crashing you need to prioritise by longest path first, 4:50 but after that we need to prioritise either the burst/merge node or simple node. Here answer would be same but still for other problems it may differ.

    • @The_Business_Doctor
      @The_Business_Doctor  Год назад +1

      Yes, depending on the problem and parameters there can be more than one combination of crashing activities

  • @damadumdum
    @damadumdum Месяц назад

    so when finding the fastest duration, we stop crashing when the critical path has been fully crashed?

    • @The_Business_Doctor
      @The_Business_Doctor  Месяц назад

      I’m not sure what you mean by the “fastest duration”. Perhaps you mean the shortest possible time and that would be determined when you have crashed all paths and you might end up with more than one critical path. When you have multiple critical paths a you must be able to crash each by the same time to keep crashing to get to the shortest possible or project completion time (duration).

  • @HamzaScuderia
    @HamzaScuderia 10 месяцев назад

    Hi,
    if there was a scenario that at the end of crashing A-D-G and B-E-G paths (where both = 9 weeks) were you to find that the C-F path also contains 9 weeks (in which case all 3 paths are now critical paths), how would you go about it? Will you now reduce F as well as reduce E (from the B-E-G path) or is that not possible? Thanks

    • @The_Business_Doctor
      @The_Business_Doctor  10 месяцев назад

      If the critical paths are all 9 weeks, if you had the ability to crash activities you would have to crash an activity on EACH path so they all get reduced. You can’t crash F by one week (making C-F 8 weeks) and leave ADG and BEG at 9 weeks. The challenge is to be able to balance all of the critical paths.
      Hope this helps.

  • @sphesihlepaya4848
    @sphesihlepaya4848 28 дней назад

    Hi, whilst you made a mistake on crash cost per week on B. Does it affect things? since you wrote 400 instead of 600

    • @The_Business_Doctor
      @The_Business_Doctor  23 дня назад

      I did make a mistake there and the crash cost of B should be $600 instead of $400 but it doesn’t affect the final solution since B never gets crashed.
      Thanks for pointing out the error and hope this helps.

  • @user-dp2ln7yv3z
    @user-dp2ln7yv3z Год назад +1

    When crashing G, if the max crash for G is 2 weeks, why aren’t we subtracting 1 week from each critical path to get a 11 week critical path?

    • @The_Business_Doctor
      @The_Business_Doctor  Год назад +4

      Hi there. If you go to 8:20 in the video, you can see that G is crashed by 2 weeks getting down to 10 weeks. If you're asking why it wasn't crashed earlier, that's because D was less expensive.
      Hope this helps.
      Mark

  • @lokmanhakim8576
    @lokmanhakim8576 6 месяцев назад

    Hi sir, may i ask - how do we get the Crash Time Values (in column 2) ?
    Also must the Duration Unit be standardized to weeks? or can it be any other time unit (i.e. man-days)?

    • @The_Business_Doctor
      @The_Business_Doctor  5 месяцев назад +1

      Hi there. The crash time values are provided, so there are no calculations required. You can use any unit you like: days, weeks, months, etc..
      Hope this helps.
      Mark

  • @SearaboKgekoane
    @SearaboKgekoane Год назад +1

    Well explained, thank you

  • @tehdavidshow
    @tehdavidshow Год назад

    I have an example from my homework that is throwing me off. For activity D, the normal duration is 1 (day) and the crash is 3 (days). if I take the crash and subtract the normal duration I get -2 which doesn't seem right. Any advice on how to do that properly? All the rest of the activities have the crash duration smaller than the normal duration.

    • @The_Business_Doctor
      @The_Business_Doctor  Год назад

      Hi David,
      Well that is an interesting one. I suspect it might be a typo. I suggest you confirm with your instructor on that one.
      Mark

  • @noorasilahizatie4979
    @noorasilahizatie4979 Год назад

    Hello sir, one question. When you crash E by 1 week, why you also minus the ADG path because theres no E in that path.

    • @The_Business_Doctor
      @The_Business_Doctor  Год назад +1

      Hi there. At some point you can end up with more than one critical path, so when you crash A, that reduced the time along A-D-G, but then B-E-G must also be reduced. You might be thinking of the part in the video where just before I take the time of B-E-G I took 1 off A-D-G -- that's because I missed updating my little crash table. Hope this helps.
      Mark

  • @maramben4618
    @maramben4618 2 года назад +1

    why can't we crash more of B and E I don't clearly understand the reason ?

    • @The_Business_Doctor
      @The_Business_Doctor  2 года назад +2

      Hi Maram,
      If you look at the summary at around 10:00 in the video, you'll see that after crashing to 7 weeks, both paths A-D-G and B-E-G are critical at 9 weeks. While you could spend money to crash B and E and get below 9 weeks you would be wasting the money because you cannot crash any more on A-D-G so it would still be 9 weeks. At this point you have more than one critical path and to be able to continue crashing, you must be able to crash activities on both paths otherwise you cannot proceed.
      Hope this helps.
      Mark

  • @kennethkayeramos2858
    @kennethkayeramos2858 Год назад

    Hello sir. I have a question, the difference between normal time and crash time is the counts of crash?

    • @The_Business_Doctor
      @The_Business_Doctor  Год назад

      Yes. If the normal time is 10 days and the crash time is 8 days then the activity can be crashed by 2 days

  • @yeesenghoo6711
    @yeesenghoo6711 10 месяцев назад

    Why activity A and activity E can only reduced by 1 weeks, but both activities have crash time limits up to 3 weeks

    • @The_Business_Doctor
      @The_Business_Doctor  10 месяцев назад

      Just because an activity can continue to be crashed doesn’t make it should be because there can be other critical paths that have to be balanced so continuing to crash A and E won’t reduce the project time any further. You must carefully observe when other paths become critical and then try to crash activities line on all the path risk or find activities on each path that can be crashed by the same time to keep the path times balanced.

    • @tinotendakanyemba7948
      @tinotendakanyemba7948 6 месяцев назад

      Hello Sir, So do you mean that every time we crash separate activities when we have 2 critical paths like we did for E and A we just crash once for both because in this case we had crash time limit of 3 weeks which we could do for both A and E to leave us with 7 not 9 weeks but we just crashed 1 week not 3

  • @SystemsProjectEngineer
    @SystemsProjectEngineer 2 года назад +2

    Very well done.

    • @The_Business_Doctor
      @The_Business_Doctor  2 года назад +1

      Thank you! If you haven’t already, please consider subscribing!

  • @jyotinegi7413
    @jyotinegi7413 2 года назад

    when crashing a project do we have to concentrate on task with least expensive gradient or path with least slack?

    • @The_Business_Doctor
      @The_Business_Doctor  2 года назад +5

      Hello Jyoti,
      You have be very careful with crashing. You would concentrate on the lest expensive crash cost that is ON the critical path (i.e. The path with zero slack). As you crash activities, the critical paths will change (you might end up with multiple critical paths) and you might have to move to a different path to find the next viable activity to crash. Ideally, you can crash a single activity that is on multiple critical paths.
      Crashing an activity just because it is the least expensive but isn't on the critical path is a waste of money because it won't reduce the project completion time.
      Hope this helps.
      Mark

  • @na50r24
    @na50r24 11 месяцев назад

    Wait a second:
    4:05
    The critical path is ADG?
    But you only did the forward pass, didn't you? Is that sufficient enough to determine the critical path?
    What about the backward pass?

    • @The_Business_Doctor
      @The_Business_Doctor  11 месяцев назад +2

      You only need to do a forward pass as long as you go through all the paths. The longest path is the critical path. You really only need to the the backward pass to determine what the slack for an activity is. All activities in the critical path will have zero slack but the other ones need the backward pass to determine the slack.
      Hope this helps!

  • @outofshadows2598
    @outofshadows2598 2 года назад +1

    Very well explained

  • @joudham
    @joudham Год назад

    why are the last two crashings for A and E considered 1 week together?

    • @The_Business_Doctor
      @The_Business_Doctor  Год назад

      Hi Joud. This is because at some point there is more than 1 critical path and to reduce the time by one week either 1 task that is common to both paths must be crashed or 1 task on each path must be crashed. In this case if you crashes A only that path would be reduced by one week but the path E is on will not.
      Hope this helps
      Mark

    • @kathestrella-ju8bc
      @kathestrella-ju8bc Год назад

      @@The_Business_Doctor why isn't E multiplied by 3 weeks?

    • @The_Business_Doctor
      @The_Business_Doctor  Год назад

      @@kathestrella-ju8bc If you crash E by more than 1 week without crashing another activity an a different path, you would be wasting your money because the project time will not be reduced. Hope this helps.

  • @sanajan8491
    @sanajan8491 9 месяцев назад

    Why are we crashing D by just 1 week when we can crash it by 4 weeks?

    • @The_Business_Doctor
      @The_Business_Doctor  9 месяцев назад

      If you crash D the project time will not be reduced because at least one other path is still critical. You have to crash activities on each critical path by the same amount for the project time to reduce. We try to crash activities that are common to multiple critical paths to save crash cost but that’s not always possible.

  • @olo1135
    @olo1135 Год назад

    why we stop at 7 weeks and why did not go further why dont you tried to reduce E or B more

    • @The_Business_Doctor
      @The_Business_Doctor  Год назад

      Hi Olo,
      You can't go any further because the remaining activities that could still be crashed are not on the critical path. So you COULD pay money to complete them in a shorter time period, but it won't reduce the total project time, so you would be wasting your money. A valid reason for paying extra to free up the resources to complete those activities earlier might be to allocate the resources to another project.
      Hope this helps.
      Mark

  • @yunggoth8505
    @yunggoth8505 2 года назад +1

    Could you tell me the name of the book please?

    • @The_Business_Doctor
      @The_Business_Doctor  2 года назад +2

      The textbook for that course was Heizer, J., Render, B., Munson, C., & Griffin, P. (2020) Operations Management (3rd Canadian edition)

  • @AmirB-yc3yp
    @AmirB-yc3yp 11 месяцев назад

    hi may i know the textbook you refer for the exercise. thanks!

    • @The_Business_Doctor
      @The_Business_Doctor  11 месяцев назад

      Hi there,
      The textbook for that one is:
      Operations Management: Sustainability and Supply Chain Management, Third Canadian Edition by Hweizer, Render, Munson, and Griffin ISBN 978-0-13-483807-6
      Hope this helps.
      Mark

  • @FABRlCE
    @FABRlCE 11 месяцев назад

    column 6, 2nd difference is incorrect though, right?

    • @The_Business_Doctor
      @The_Business_Doctor  11 месяцев назад

      Hi there. Yes there is a typo there. Someone else had noted that before in a previous post which I confirmed. It doesn’t change the answer, however.

    • @FABRlCE
      @FABRlCE 11 месяцев назад +1

      @@The_Business_Doctor super 💯

  • @SS-pn7ss
    @SS-pn7ss 8 месяцев назад +1

    Thank you so much

  • @riskaoktaviani1816
    @riskaoktaviani1816 Год назад

    i think max crash is 8 weeks not 7 weeks
    because total max crash is $1600

    • @The_Business_Doctor
      @The_Business_Doctor  Год назад

      Hi Riska, the maximum this project can be crashed is by 7 weeks to end up at a 9 week project time. The solution is correct.
      Mark

    • @PoeEdogawa
      @PoeEdogawa 8 месяцев назад

      @@The_Business_Doctor Hello sir, can you explain why (in detail)? I'm so sorry, I'm still a little bit confused. Thank you in advance

  • @serenitytercias2012
    @serenitytercias2012 2 месяца назад

    hi what if you are not provided normal cost

    • @The_Business_Doctor
      @The_Business_Doctor  2 месяца назад

      Hi there,
      Well if you don’t know the normal cost you have to then be told the incremental cost to crash otherwise you can’t solve the problem.
      Hope this helps.
      Mark

  • @joeyanneitorralba5861
    @joeyanneitorralba5861 Год назад

    Hi! I would like some help in a project management problem. Can i send it via email?

    • @The_Business_Doctor
      @The_Business_Doctor  Год назад

      Sorry, I wish I could but I’m at my maximum capacity right now.

  • @moyou5405
    @moyou5405 6 месяцев назад

    I still think your speed is way too fast

  • @zain4494
    @zain4494 2 года назад

    thanks bro

    • @The_Business_Doctor
      @The_Business_Doctor  2 года назад

      You're welcome, Zain! If you like the videos, please consider subscribing!

  • @aronkovacs9604
    @aronkovacs9604 Год назад

    why the monkey bits is this called Crashing? :/

    • @The_Business_Doctor
      @The_Business_Doctor  Год назад

      Good question! We'll have to ask the Project Management Gods about that one.

  • @sabelozondo7179
    @sabelozondo7179 2 года назад

    Kindly drop your email, please. I need help with project management activities.

    • @The_Business_Doctor
      @The_Business_Doctor  2 года назад +1

      Hi Sabelo, you are free to email me at mark@strategema.ca to let me know what you are looking for.