Thx Eng Hani but could you elaborate why 18 days is not compensable (although it is excusable) and this delay (18 days) is caused by client and that's why contractor has the right to claim for cost also since project finish date will shift 18 days further
Thx Eng Hani but could you elaborate why 18 days is not compensable (although it is excusable) and this delay (18 days) is caused by client and that's why contractor has the right to claim for cost also since project finish date will shift 18 days further
You didnt explain why there was an 18 day impact on a 14 say event
Sir can u please a practical video for me where project finished date change from March to February. 1 month before the project end date
Hello Engineer, check your critical path and adjust it to fit your planned finish date.
@PlanningengineerNet okay sir