@@vbelectricalcontractcompany bro ORU veetuku full wiring work Panna evlo amount charge panlam single phase Ku evlo amount 3 phase Ku evlo amount charge panlam sollunga bro kinjam detail a
@@mohanpuyalkurvin6662 Bro ippo oru 10×10 room iruku na athu vanthu oru sathuram ok va, Oru sathurathuku Electrical and plumbing work 4500 rs Bro But bathroom ku thani amount charge pannuvom Oru simple 3 Phase main board ku 3500 rs ,single Phase 1500 bro
@@vbelectricalcontractcompany plumbing work illama electrical work mattum Panna evlo amount charge panlam aprom single phase main board connect Panna 1500 a 10*10 room size illama aprom 3 phase na 3 3500 vaangalama 10*10room size Ku amount serthu room size thani aprom main board Ku thaniya amount vangalama
Hi ji, Pipe enna company use pannirukenga. Oru pipe, fan hook, Junction box, 90 bend oda price evlonu solla mudiyumaa??. Thnk u.. waiting for u r reply.
Bro electrical wiring ku Chennai la oru sqft evalo charge pannanum, including material and without material (only labour charge) ithu Rendume evalo amount la work pannanum detail sollunga.....
Bro neenga material contract edutha ungaluku oru electrical shop theriyanum bro appothaan edukka mudium , Electrical labour charge only oru sathurathuku 2500 to 3500 pannalam
Super bro thanks for good information
super thala💪
Slab thickness?
Yow thilak
Thalaiva innum mela mela poonga lifela
Nalla varum pa neengalam
Thanks bro
Ena bro thankslam solli asinga paduthureenga
Bro main line service Ku pipe gi podama roof pipe podringa apdi potta EB line kudupangla
Bro EB line 5 metter mattum tha concealed pannanum athuku Mela wire ullaiye poga kudathu
@@vbelectricalcontractcompany ok bro
7அடி மட்டம் சைடு சிளாப் லைட் எப்படி வைப்பது
Bro pipe laying andha veetuku electrical work pandravanga pannanuma illa mesthiri pannikudupangla
Bro engineer's Building iruntha avangale plan tharuvanga apadi illana nambale layout podanum bro
@@vbelectricalcontractcompany bro ORU veetuku full wiring work Panna evlo amount charge panlam single phase Ku evlo amount 3 phase Ku evlo amount charge panlam sollunga bro kinjam detail a
@@mohanpuyalkurvin6662 Bro ippo oru 10×10 room iruku na athu vanthu oru sathuram ok va,
Oru sathurathuku Electrical and plumbing work 4500 rs Bro
But bathroom ku thani amount charge pannuvom
Oru simple 3 Phase main board ku 3500 rs ,single Phase 1500 bro
@@vbelectricalcontractcompany plumbing work illama electrical work mattum Panna evlo amount charge panlam aprom single phase main board connect Panna 1500 a 10*10 room size illama aprom 3 phase na 3 3500 vaangalama 10*10room size Ku amount serthu room size thani aprom main board Ku thaniya amount vangalama
@@vbelectricalcontractcompany bro apo ORU square fit Ku 25 rupe amount charge padringla neenga blumbing work illama
Hi bro
Oru doubt
roof counseled pipe la spring evlo feet pogum and evlo bend cross aagum.
40 feet lenth la 3 bend erukku ,ethula spring poguma
40 feet 3 bend bro new spring ga iruntha pogum but old spring ga iruntha pogathu
Hi ji,
Pipe enna company use pannirukenga. Oru pipe, fan hook, Junction box, 90 bend oda price evlonu solla mudiyumaa??.
Thnk u.. waiting for u r reply.
Ji, ippo oru pipe oda price pathingana oru area ku oru price ippo na use panna thu Neroplast company Bro
Bro electrical wiring ku Chennai la oru sqft evalo charge pannanum, including material and without material (only labour charge) ithu Rendume evalo amount la work pannanum detail sollunga.....
Bro neenga material contract edutha ungaluku oru electrical shop theriyanum bro appothaan edukka mudium ,
Electrical labour charge only oru sathurathuku 2500 to 3500 pannalam
bro pipe size bro pls
1 inch and 3/4 pipe tha use pannuvom but 3phase main board incoming line ku 1¹/⁴ use pannuvom bro