Schedule Comparison Dashboard XER Tool: Analyzing and Reporting Project Progress Baseline Comparison

Поделиться
HTML-код
  • Опубликовано: 10 дек 2024

Комментарии • 15

  • @SoftEdemy
    @SoftEdemy  Год назад

    Subscription link : www.softedemy.com/product/detailed-schedule-comparison-report-xer-tool/

  • @durgeshk9204
    @durgeshk9204 Год назад

    kindly also answer this query, is there any trick to fill same dates to multiple activities?

    • @SoftEdemy
      @SoftEdemy  Год назад

      Assign same relationship if all activities have same start and finish
      If their are some specific dates you want to add into your project and freeze them, Calculate their Float manually on excel than create a relationship by using Excel and import in P6 as faster way.

  • @durgeshk9204
    @durgeshk9204 Год назад

    Is there any trick to change Activity status from completed to not started at one go?

    • @SoftEdemy
      @SoftEdemy  Год назад

      Yes watch the video in this link
      ruclips.net/video/5iuoLDMbXJA/видео.html

    • @durgeshk9204
      @durgeshk9204 Год назад

      @@SoftEdemy thanks a lot, your suggested video really very helpful and also thanks for your early response.

    • @SoftEdemy
      @SoftEdemy  Год назад

      @durgeshk9204 welcome,we will try to keep our the attitude forever

    • @durgeshk9204
      @durgeshk9204 Год назад

      @@SoftEdemy can you also answer this query, "Do you want to add a Start On or After constraint on 14/Jan/2023 to hold the activity in place? what does this mean?

    • @SoftEdemy
      @SoftEdemy  Год назад +1

      @@durgeshk9204 It means he asking to hold on the activity dates of specific activity on or Start after constraint 14/Jan/2023 .By applying any constraint the Float will be zero the activity will be strict to near the date specific early start or late start.