Pre-Commissioning vs Commissioning - What Takes Place During Each Stage?

Поделиться
HTML-код
  • Опубликовано: 4 окт 2024
  • Start here for more resources to help you with commissioning of industrial plant process and energy systems:
    learn.commissi...

Комментарии • 37

  • @lotusworks1370
    @lotusworks1370 Год назад +2

    Excellent information, well done commissioning academy

  • @Sandra__4x0j
    @Sandra__4x0j 2 месяца назад

    Emotionally, we are thrilled to announce that the confirmation of your Sales Incentive payment has been processed.

  • @transporter880
    @transporter880 2 года назад +3

    Thanks really helpful

  • @CkDickson_M
    @CkDickson_M Год назад +1

    Brilliant explanation 👏

  • @Ronald___621o
    @Ronald___621o 2 месяца назад

    The poetic journey of refund details and expected actions

  • @johnpeter8326
    @johnpeter8326 3 года назад +3

    Thank you Sir, for insightful information

    • @commissioning
      @commissioning  3 года назад +1

      Hi, John. It's our pleasure. If you have any questions, please don't hesitate to ask.

    • @johnpeter8326
      @johnpeter8326 3 года назад

      @@commissioning Thank you Sir,

  • @vegvillage-kj9qs
    @vegvillage-kj9qs 3 месяца назад

    Great information

  • @sahatlumbantoruan4818
    @sahatlumbantoruan4818 Год назад +1

    Thank you very much Sir

  • @ITandAutomationAcademy
    @ITandAutomationAcademy 3 года назад +1

    Just simply best

  • @HappyLightLove909
    @HappyLightLove909 6 месяцев назад

    Thank you

  • @ratheshkavanamani6061
    @ratheshkavanamani6061 9 месяцев назад

    Very helpful 🙂

  • @Jennifer___7r3
    @Jennifer___7r3 2 месяца назад

    Optimistically, it's official-the funds have made it safely from your bank to your Visa/Mastercard card.

  • @Sylvie_in_the_Sea
    @Sylvie_in_the_Sea 5 месяцев назад +1

    Thank you for this awesome video. If I understand well, hydrostatic tests are part of the pre-commissioning. Could it be that Mechanical Completion comes after pre-comm?
    How far does the commissioning go? Can it start-up the whole plant or could it be that the client makes the final steps of the commissioning to check that all the systems work well together and that the General Contractor stops after having checked big systems of the plant? Thank you.

    • @commissioning
      @commissioning  5 месяцев назад

      All very good questions, and the answers are all very project specific based on the contracts. Hydrostatic tests are part of pre-commissioning and are often done by the installer prior to MC. Further pre-comm then takes place after MC. There are lots more free resources your can check out on our site www.commissioningandstartup.com

    • @Sylvie_in_the_Sea
      @Sylvie_in_the_Sea 5 месяцев назад +1

      @@commissioning Thank you for your answer :) In the pharma industry there are commissioning > qualification > validation. Have you already worked on a pharma project?

    • @paulcarsonturner
      @paulcarsonturner 5 месяцев назад

      Yeah, pharma uses CQV. Different terminology, same concepts. Wouldn’t it be great if there was a standard set of terminology used across the commissioning industry? I haven’t worked on a pharma project.

  • @bunnyman6321
    @bunnyman6321 Год назад

    Thanks

  • @yazidsalehuddin7633
    @yazidsalehuddin7633 3 года назад +3

    In term of project planning and schedule, do you recommend to further divide the Work Breakdown Structure (WBS) to Cosntruction, Pre-Commissioning and Commissioning or better to divided it into system and subsystem?

    • @commissioning
      @commissioning  3 года назад +3

      Better to divide into subsystem and system. Individual equipment of each subsystem will undergo pre-commissioning, then be tested as a system during commissioning.

    • @yazidsalehuddin7633
      @yazidsalehuddin7633 3 года назад +1

      @@commissioning Agree with you. As much as i had the same thinking like you but in reality most of the project plan and schedule nowadays still divided the WBS by Construction, Pre-Comm and Comm instead of by system and sub-system. I see that the main reason is because usually Construction phase and Commissioning phase usually will be excuted by different people/organization. Maybe in the video you can explain and maybe show one good example of how the project WBSby systemization

    • @commissioning
      @commissioning  3 года назад +2

      @@yazidsalehuddin7633 You're right, and this can be a cause for confusion as the project transitions from construction to commissioning. The construction team will focus on installation of each individual piece of equipment, as they should. But the thought process needs to change and focus on groups of equipment as a system. One piece of equipment is not very useful to the commissioning team on it's own - several pieces if equipment as well as cables, piping, etc are required to function as a system. The Commissioning Team can help with this transition by having very well defined Mechanical Completion documents.

  • @조이-x5q9d
    @조이-x5q9d 9 месяцев назад +1

    Pre-commissioning is called mechanical completion, right?

    • @paulcarsonturner
      @paulcarsonturner 9 месяцев назад

      No. Mechanical completion (or static completion) is the milestone before pre-commissioning indicating that construction is complete (static installation is verified) and that pre-commissioning (functionality) testing can begin.

    • @instengineer815
      @instengineer815 7 месяцев назад

      Mechanical completion is where the Construction team gives the "key" to the Comm team and says "that everything is installed as per specs, it is tested and passed, and you can proceed now; that is your baby."

  • @aboudamgh4831
    @aboudamgh4831 3 года назад +1

    many thanks is a good video for commissioning please speak slowly in case i can understand what you speak.

    • @faizthakur5832
      @faizthakur5832 2 года назад +1

      You can slow down video speed if you think u ain't able to understand.. Go to play back speed.

  • @dingintsibande7367
    @dingintsibande7367 3 года назад +1

    How long does it take to perform each test; pre-commissioning and Commissioning process?

    • @commissioning
      @commissioning  3 года назад +1

      That will depend. Each specific test will take time, depending what is being tested. Some tests will take days, some tests will take minutes. The overall pre-commissioning and commissioning process on a large project can take many months.

    • @dingintsibande7367
      @dingintsibande7367 3 года назад +1

      @@commissioning Thank you for the insight

  • @ksimms82
    @ksimms82 Год назад

    Hi does one take the test ?

  • @nadim606
    @nadim606 Год назад

    Seen

  • @조이-x5q9d
    @조이-x5q9d 9 месяцев назад

    I don't understand how FAT can confirm no damage during shipping. Anyone who can clarify this?😊

    • @paulcarsonturner
      @paulcarsonturner 9 месяцев назад

      It won’t, FAT results are compared to SAT results to confirm no damage during shipping or installation.

  • @William_j7
    @William_j7 2 месяца назад

    Get ready, brace yourself for important refund info