Boiler Emergency Handling During Malfunction of Feed Control Valve || FCV खराब होने पर क्या करे?

Поделиться
HTML-код
  • Опубликовано: 26 янв 2025

Комментарии • 25

  • @kartikmahale6340
    @kartikmahale6340 2 года назад +2

    Due to moisture available in service air
    We used instrument air

  • @narendraverma6857
    @narendraverma6857 2 года назад +1

    Excellent💯 sir

  • @Viralreact_facts
    @Viralreact_facts 10 месяцев назад +1

    Very informative video for fresher like me

  • @sonalchakraborty3142
    @sonalchakraborty3142 5 месяцев назад

    Pressure increase hone k karan agar drum lvl low jata h toh hp lp bypass line me lena h... Open karna h.. vent itne high preasure me thode kholte hai..

  • @shivaprachande6898
    @shivaprachande6898 2 года назад +1

    Superb🙏

  • @kaushalrathod8668
    @kaushalrathod8668 2 года назад +1

    Informative video .. thanks sir 👍

  • @JitendraKumar-er1yy
    @JitendraKumar-er1yy 9 месяцев назад

    Thanks

  • @PRAVINKUMAR-fc5bz
    @PRAVINKUMAR-fc5bz Год назад

    So nice video

  • @kaushalrathod8668
    @kaushalrathod8668 2 года назад +1

    Sir please make video on NPTI.

  • @sidduganachari1702
    @sidduganachari1702 2 года назад +1

    Please upload desk operation procedure in supcon software or any software

    • @PowerPlantGuide
      @PowerPlantGuide  2 года назад +1

      Sorry frnd, it is not possible due to Plant privacy. 🙏

  • @shailendrajadon3599
    @shailendrajadon3599 2 года назад +1

    Informative video .......

  • @sonaliverma708
    @sonaliverma708 2 года назад +1

    Nice 👍

  • @mykitchengardenbonsaipetsl2505
    @mykitchengardenbonsaipetsl2505 24 дня назад

    Water supply control valve by pass may not be provided on some feed water system.
    If by pass is provided then open it as per the load demand feed water demand.
    Over feeding on full load can trip boiler drum high level to avoid carry over to turbine through Super heated steam.
    If drum level low occurs then FC must be open on Man mode or Start Stand by feed pump with in some seconds.
    We have been facing these all situations.We operated 1000 Ton/h feed with two fw pumps like 510 ton/h each pump output.
    If drum level low not controlled then boiler MFT observed to save boiler tubes bulging.

  • @pratapkumar6501
    @pratapkumar6501 2 года назад +1

    Hi sir...
    I have back dated boiler attender experience certificate (2017-2019) , now can i apply for 2nd class boiler exame..?
    Is that ex.certificate is valid .?