Excellent videos 👌👏 The perfect channel on youtube I can say for those who just started their career in sap mm s4hana module. I Highly appreciate your efforts sir. Ive just started my sap journey in mm module and I was looking for the best content and here I got yaa chanel, it would help every fresher / beginner student to gaim the knowledge. THANKS TO YOU !
in the cutover period where will you create the open POs .. is it in the new SAP system i.e S4Hana or in the existing system i.e either SAP ECC or another system? Do you have any videos where you have showed the business scenarios that you talked in this videos
New S/4 HANA system. We try to keep that period as short as possible. We need to focus on last 1-3 years data as per the business requirement along with those few days. Finally everything must be done one day before Go-Live. You can check this course for better learning. SAP Implementation Process Training with Sample Documents www.udemy.com/course/sap-implementation-process-training-with-sample-documents/?couponCode=BESTGANI
Go-Live date is like you start using the car but the showroom person tests and drive till your home etc. during cutover time. 😁. You check my implementation course with cutover properly to understand. Thanks.
Excellent videos 👌👏 The perfect channel on youtube I can say for those who just started their career in sap mm s4hana module. I Highly appreciate your efforts sir. Ive just started my sap journey in mm module and I was looking for the best content and here I got yaa chanel, it would help every fresher / beginner student to gaim the knowledge. THANKS TO YOU !
Thanks Kunal for your great words.
Excellent video. Please make more videos upon L1 support consultant as. We want to see more problems examples. Thank you sir
Very nice and informative Video
Content was good ....and we are waiting for activate methodology bro...
At high level, not much differences between ASAP and Activate so no need to worry much. Anyway I will plan a video soon.
in the cutover period where will you create the open POs .. is it in the new SAP system i.e S4Hana or in the existing system i.e either SAP ECC or another system?
Do you have any videos where you have showed the business scenarios that you talked in this videos
New S/4 HANA system. We try to keep that period as short as possible. We need to focus on last 1-3 years data as per the business requirement along with those few days. Finally everything must be done one day before Go-Live.
You can check this course for better learning.
SAP Implementation Process Training with Sample Documents
www.udemy.com/course/sap-implementation-process-training-with-sample-documents/?couponCode=BESTGANI
where will you create the existing pos in the cutover period? for example, the cutover period is from October 15th to 31st October?
New System.
@@GaneshSAPMMWM Thanks.. I thought the new system would be available on GOlive i.e on 1st November
Go-Live date is like you start using the car but the showroom person tests and drive till your home etc. during cutover time. 😁.
You check my implementation course with cutover properly to understand. Thanks.
@@GaneshSAPMMWM you always make your audience happy. Thanks Ganesh. Where will I check the implementation course with cutover