  • @Mitch-Hendren
    @Mitch-Hendren 7 месяцев назад +4

    Im ancient enough to remember it getting built . Full of delays due to construction issues.5 years late opening fully (sound familiar ?) Maybe not as strong as they thought it was.
    State of the art at the time . Dental hospital too . Pure brutalist concrete . The royal infirmary which it replaced stayed for nearly a century , this monolith lasted for only 53 years .. boiler house was fascinating though 😉

  • @kenbuckley2211
    @kenbuckley2211 7 месяцев назад +5

    The NHS Trust said it was a controlled demolition, tell that to any people walking by with all that dust

    • @caithnessrailrambler2698
      @caithnessrailrambler2698 7 месяцев назад +1

      I don't think the big machine would had been close if it was a controlled demolition at the time. Definitely something went wrong.

    • @veryhighguy
      @veryhighguy  7 месяцев назад +1

      it seemed well under control today when i had a look but i do think something went wrong. I am no expert but if you look on the video the wall gave way two floors down where it was windows (1:36). i personally thing they gave way.

    • @stephensmith4480
      @stephensmith4480 7 месяцев назад +2

      Something definitely went wrong there, maybe stress cracks that just gave way to the downward force of all that weight above. Nobody hurt, that's the main thing.

    • @caithnessrailrambler2698
      @caithnessrailrambler2698 7 месяцев назад

      Yeah i watched it very closely it looked like wall closed in and the whole lot went with it.​@veryhighguy

    • @caithnessrailrambler2698
      @caithnessrailrambler2698 7 месяцев назад

      ​@@stephensmith4480I think so too be lots of stress and weight on it and just gave way.

  • @Papario1113
    @Papario1113 7 месяцев назад +2

    Brilliant. Thanks for sharing. At 3.01 into the video am I going crazy or does a long arm appear to reach across ?

    • @steveb6027
      @steveb6027 7 месяцев назад +2

      that was someone closing the window it was being recorded through

    • @veryhighguy
      @veryhighguy  7 месяцев назад

      yes it was a reflection

    • @Papario1113
      @Papario1113 7 месяцев назад +1

      I thought I was going mad and a huge arm came down haha. Need to stay off the meds lol. Thanks!

  • @keithdouglas7154
    @keithdouglas7154 7 месяцев назад +1

    Another great video. Does anyone know what will happen with the site.

    • @veryhighguy
      @veryhighguy  7 месяцев назад +1

      it will become a training and teaching complex for future doctors

    • @keithdouglas7154
      @keithdouglas7154 7 месяцев назад

      @@veryhighguy thank-you

  • @christopherpitchford8859
    @christopherpitchford8859 7 месяцев назад +1

    What comes shooting out at the three minute mark?

    • @veryhighguy
      @veryhighguy  7 месяцев назад

      it was a reflection from the window.

  • @dominicboyle3485
    @dominicboyle3485 7 месяцев назад +1

    Been watching this for the last 5 weeks, some dodgy pushing of concrete pillars over during that time, surely better doing top to bottom, one floor at a time. Dont fancy their chances when working right behind Clatterbridge etc

  • @caithnessrailrambler2698
    @caithnessrailrambler2698 7 месяцев назад +1

    A scary monent there hope the operator is ok. Might had gived him a fright

  • @robfalcon3404
    @robfalcon3404 7 месяцев назад +2

    That dust ell be bad wow

    • @veryhighguy
      @veryhighguy  7 месяцев назад +2

      Full of asbestos

    • @johntyrrell6591
      @johntyrrell6591 7 месяцев назад +3

      There will be some Health & Safety Investigation there. Lucky there weren't any demolition guys around when that fell

    • @heavyhaulage1
      @heavyhaulage1 7 месяцев назад +1

      @@veryhighguy all asbestos would have been removed

    • @veryhighguy
      @veryhighguy  7 месяцев назад

      @@heavyhaulage1 it was all in the concrete

  • @Bassisace1
    @Bassisace1 7 месяцев назад +1

    Let’s hope that no individuals were hurt.
    I would think that site safety will be really tightened up after this. Hopefully, the works will progress smoothly, from here on in.

  • @JamesAnt-tp8mp
    @JamesAnt-tp8mp 7 месяцев назад +1

    Just one of them things dsm are leading demo company old building can’t control every thjnk.

    • @GarryMcHugh-w8b
      @GarryMcHugh-w8b 7 месяцев назад +2

      I im a high reach operator that was reckless, leaving the gabble 4 story's high not tied in and cutting a column bellow, I seen it before it happened

  • @dominicboyle3485
    @dominicboyle3485 7 месяцев назад +1

    Dont think that water spray helped much lol