Estimation - One Room (2021)

Поделиться
HTML-код
  • Опубликовано: 1 янв 2018
  • To estimate the cost of any building or a structure, drawings, specifications and rates are required. Regarding the detailed estimate by long wall and short wall method and centre line method, the drawings consisting of plan elevation and section are sufficient.
    #Buildingestimation #Civiconcepts
    Follow my Facebook page : / civiconcept

Комментарии • 80

  • @mahesh5861
    @mahesh5861 4 года назад +4

    Sir, I want to construct one simple 10x12 long lasting cement block room in farm without column. With two windows and one door. Too many thefts happen so things should be strong. Please suggest idea, which materials to use and what may be total cost

  • @chandansingh1135
    @chandansingh1135 5 лет назад +6

    Thanks guru ji Aapka smghane Ka trika mast hai

  • @aayataayat452
    @aayataayat452 5 лет назад +1

    sir 1 step mai length same ku rahi....as same as in excuvation

  • @javedzaman7440
    @javedzaman7440 6 лет назад +1

    Bhai 14×12room rcc kitna karcha ata he plz guide me

  • @manojsahoo6228
    @manojsahoo6228 4 года назад +1

    13/15fit bed room re support pain kichi calom dabaku padiba ki

  • @Iemiftikhar
    @Iemiftikhar 11 месяцев назад

    Very Nicely You have explained Dear Engineer Sb. May you always stay blessed

  • @pankajgunjal2780
    @pankajgunjal2780 5 лет назад

    approximataly kitana hoga,,&this plan includes load bearing str. slab provided

  • @sandeerock2470
    @sandeerock2470 5 лет назад +1

    Sir kisi v wall ka estmat and casting kaise kre

  • @debojitsaikia6351
    @debojitsaikia6351 4 года назад

    Total length exacavation hota hai kiya? Or numbr of post excavate hota hai.

  • @KLEntertainment
    @KLEntertainment 6 лет назад +1

    this calculation for only foundation or Full room up to Uper Beam?

  • @adnanjaffar9214
    @adnanjaffar9214 4 года назад

    bhai hama plan main centre line Q draw khrne hai kis maksad k leyei

  • @prashantrohilla1637
    @prashantrohilla1637 Месяц назад

    Best ever best explaination ❤

  • @goldyoffical_
    @goldyoffical_ 3 года назад +1

    Sir platesr work kese cacluate kre

  • @hariharanhacks2654
    @hariharanhacks2654 5 лет назад +1

    I don't know why are u putting steps under foundation area like bricks but when we construction we don't use like that steps

  • @devbudha8037
    @devbudha8037 6 лет назад +2

    Very good lecture thank you soo much sir

  • @blackite598
    @blackite598 5 лет назад +1

    Sir yahan length find karne keliye what didn't we use the formula L= CL- width/2 × no.of T junction???? Pliz explain....

  • @eteshakumarmohanty8450
    @eteshakumarmohanty8450 5 лет назад +2

    Sir you are outstanding

  • @APHOMELAND
    @APHOMELAND 4 года назад +1

    pl continue u estimate for one room, very good explaint

  • @aatifawan781
    @aatifawan781 6 лет назад +1

    nice bro keep it up

  • @nagkambhampati958
    @nagkambhampati958 6 лет назад +2

    sir please tell me about with mortar volume how many bricks are used in
    the given plan

  • @VARUNKUMAR-uj4kz
    @VARUNKUMAR-uj4kz 4 года назад +1

    Sir please clear the concept of estimating the building with walls of different thickness and with different foundation, all the videos are made with only 1-2 similar examples, no one is moving ahead of these things

  • @neemoking4263
    @neemoking4263 3 года назад

    clean explanation sir

  • @abineshkannan7098
    @abineshkannan7098 5 лет назад +1

    septic tank rectangle circular video karo bai

  • @pandumurmu
    @pandumurmu 5 лет назад +1

    Thank you

  • @HASAN_ARCHITECTS
    @HASAN_ARCHITECTS 2 года назад

    Door window deduction to kr dete?

  • @kajalyadav1565
    @kajalyadav1565 3 года назад +3

    Deduction methods estimating p/z explain in breify.

  • @thamizharul4553
    @thamizharul4553 5 лет назад +2

    tamil laungage full building estimate sir plz

  • @arsahibarora3353
    @arsahibarora3353 2 года назад

    Sir HSR ke according bhi ek video bnaiye

  • @kishoreysn7801
    @kishoreysn7801 4 года назад +1

    We take 200mm extra on either side of the pcc bed for excavation , which gives 0.9+0.2+0.2 = 1.3

  • @DesignerDekhrekh
    @DesignerDekhrekh 4 года назад

    Nice vedio # civilstudy

  • @renudevi7532
    @renudevi7532 4 года назад +1

    Sir video m down se apne channel ka logo jata diya karo video dekhne m problem hoti h

  • @danishjacky9033
    @danishjacky9033 5 лет назад +2

    Sir jis room ki foindation m offset one side hote h uska kaise krenge bataiye sir

  • @harshadakadam6030
    @harshadakadam6030 3 года назад

    Please give me plan elevation and section n also Footing details plz plz

  • @ajisback9262
    @ajisback9262 2 года назад +1

    Thanks 😊☺️👍🙏

  • @AmitGupta-cj5ey
    @AmitGupta-cj5ey 5 лет назад +2

    Very nice sir

  • @Alexa-sp7fr
    @Alexa-sp7fr 5 лет назад +1

    Thanks

  • @muruganrenganathan3178
    @muruganrenganathan3178 4 года назад +2

    You not add P.c.c.

  • @bhagatthakur8772
    @bhagatthakur8772 5 лет назад +1

    Sir y center k bhar wali distance add krni hogi pecche

    • @Civiconcepts
      @Civiconcepts  5 лет назад

      Becoz we calculated c/c for 0.3 wall, pcc width is different so we required correct it

  • @parveshcivile7777
    @parveshcivile7777 6 лет назад +1

    Very good bro👍👍👍

  • @devbudha8037
    @devbudha8037 6 лет назад +1

    Sir make a video how to estimate bulding center line method

  • @indadhussain4103
    @indadhussain4103 5 лет назад

    Sir wall 0.3 kaisa hotha sir 9 inch wall ka 0.2 hothans

  • @aatifawan781
    @aatifawan781 6 лет назад +1

    bro send me junction video of this tuttorial and also tell me how to calculate the bricks of well

  • @NEETURAWAT-hq6mr
    @NEETURAWAT-hq6mr 6 месяцев назад

    @7.51 m ek chiz glt h
    It will be 19.2 x 0.60x 0.20 = 3.456

  • @Iemiftikhar
    @Iemiftikhar 11 месяцев назад

    I hv subscribed you channel

  • @samimahamad6889
    @samimahamad6889 3 года назад

    Can't say . (point) fifteen... always use to say point one five

  • @serajkha9053
    @serajkha9053 4 года назад

    aapki awaj bahut slow aata hai plz thora sa apna volume badha dijie

  • @biswajitmondal8749
    @biswajitmondal8749 5 лет назад

    Thanku u sir....very helpful

  • @debbatijyothi7674
    @debbatijyothi7674 3 года назад +1

    So what about door and window

    • @Civiconcepts
      @Civiconcepts  3 года назад

      Watch other video for detail Estimation

  • @NarendraPatel-nb1mq
    @NarendraPatel-nb1mq 5 лет назад +1

    Double room ka sir uploaded kijije sir

    • @Civiconcepts
      @Civiconcepts  5 лет назад

      Aur video hai channel subscribe karo

  • @er.yashpalsurya818
    @er.yashpalsurya818 5 лет назад +1

    Estimate of victory tower in hindi

  • @animeclips-world
    @animeclips-world 6 месяцев назад +1

    Only this
    Please more detail like
    Dpc
    Shuttering work
    Steel cutting bending fixing
    Rcc concrete on slab
    Plaster
    Rcc flooring
    Electric work
    White wash

    • @Civiconcepts
      @Civiconcepts  6 месяцев назад

      video available on channel please check

  • @thamizharul4553
    @thamizharul4553 5 лет назад +1

    sir eartwork and pcc k but next step sir

  • @mukeshprajapati8613
    @mukeshprajapati8613 4 года назад +1

    2 wall ko nikalne liy

  • @er.ajaysharmajaybalaji123
    @er.ajaysharmajaybalaji123 6 лет назад +1

    Chapter 3ka hindi

  • @moumitamitra728
    @moumitamitra728 4 года назад +1

    Sir thank you so much for this video....Simpson rule and trapezoidal rule k math k under 1 video ho to acha hota plz sir...

  • @pankajgunjal2780
    @pankajgunjal2780 5 лет назад +1

    sir 10*10 room ka kharacha kitana aayega

    • @Civiconcepts
      @Civiconcepts  5 лет назад

      Locally material rate and labour rate par depend karta hai

  • @nidhitiwari6121
    @nidhitiwari6121 5 лет назад

    Thanks sir

  • @uniquebandu7779
    @uniquebandu7779 6 лет назад

    Are bhai window deduction to kr

    • @Civiconcepts
      @Civiconcepts  6 лет назад

      Frd.. Its quantity up to ground level..how can i deduct window

  • @user-pi5jn8tt5b
    @user-pi5jn8tt5b 6 лет назад +1

    Thanks😭

  • @pauleben6115
    @pauleben6115 2 года назад

    Bro pls video update in Tamil language

  • @mithunroy2834
    @mithunroy2834 6 лет назад

    Supper

  • @hamzazahid5247
    @hamzazahid5247 6 лет назад +1

    just copying others simple qs. please bring something new :/ more advance

  • @rhymecity_4
    @rhymecity_4 2 года назад

    Teaching in Indian but seeking subscribers is done in English😂😂😂

  • @namanchauhan4716
    @namanchauhan4716 5 лет назад

    Very nice sir

  • @mif9072
    @mif9072 6 лет назад +1

    bhai ye toh basement ka method hai hame sirf ek jageh excavation karke column dena hai puura wall dig ni karni

    • @Civiconcepts
      @Civiconcepts  6 лет назад +1

      Its load bearing structure not frame structure

    • @mif9072
      @mif9072 6 лет назад

      explain about frame structure if u can..

    • @Civiconcepts
      @Civiconcepts  6 лет назад +1

      U hve to calculate qty for columns footing and multiple with no. Of columns in building