00:00 Understanding flow shop scheduling and minimizing total elapsed time 01:32 Johnson's rule guides job sequencing based on machine processing time. 03:04 Handling tie-breaking using Johnson's algorithm 04:37 Johnson's Algorithm sequence and idle time calculation 06:15 Scheduling jobs on two machines using Johnson's algorithm. 07:44 Schedule for job processing on machine b 09:13 Calculation of total elapsed time and idle time for each machine. 11:14 Johnson's algorithm helps in sequencing and finding idle time in flow shop scheduling Crafted by Merlin AI.
Great explanation, very concise!!
🙏🏻
very well explained sir. thank you
Thanks 🙏🏻
Thank you sir. Very well explained.
Thanks 🙏🏻
00:00 Understanding flow shop scheduling and minimizing total elapsed time
01:32 Johnson's rule guides job sequencing based on machine processing time.
03:04 Handling tie-breaking using Johnson's algorithm
04:37 Johnson's Algorithm sequence and idle time calculation
06:15 Scheduling jobs on two machines using Johnson's algorithm.
07:44 Schedule for job processing on machine b
09:13 Calculation of total elapsed time and idle time for each machine.
11:14 Johnson's algorithm helps in sequencing and finding idle time in flow shop scheduling