EarthWork Quantity Of A Road By Using Prismoidal Method
HTML-код
- Опубликовано: 2 дек 2024
- EarthWork Quantity Of A Road By Using Prismoidal Method @CivilConstruction
How to Calculate EarthWork Quantity of a Road by Prismoidal Method?
Earthwork Quantity of an Embankment by Prismoidal Method. Earthwork calculation by Prismoidal Method.
#EarthworkQuantity #EarthWorkOfARoad
Watch other Videos:
Earthwork Calculations For Road Works | How to Calculate Earthwork Cutting and Filling Quantity in Hindi.
👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻
• Earthwork Calculations...
Rate Analysis of BrickWork. Estimation and Costing of BrickWork.
👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻
• Rate Analysis of Brick...
Calculation of no. of bricks and Quantity of Cement & Sand in Mortar | BrickWall Calculation Formula.
👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻
• Calculation of no. of ...
Rate Analysis of Brickwork | Analysis of Rates of Brick Wall | Quantity and Costing of Brick Work.
👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻
• Rate Analysis of Brick...
Long Wall and Short Wall Method of Estimation for 2BHK House in Hindi/Urdu.
👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻
• Long Wall and Short Wa...
Estimation by Long Wall and Short Wall Method | Two rooms estimation by Long wall and Short Wall.
👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻
• Estimation by Long Wal...
Building Estimation by Center Line Method | Two rooms Estimation by Center Line Method in Hindi.
👇🏻👇🏻👇🏻👇🏻👇🏻👇🏻
• Center Line Method of ...
Social links:-
Instagram: / civilconstruction_
Facebook: / sahil.bhagat.9026
Facebook page:
/ civil-construction-108...
Telegram channel:
t.me/civilcons...
earthwork quantity of road,
quantity of earthwork for road,
calculate quantity of earthwork for road,
earthwork calculations for road works,
earthwork calculation in surveying,
earthwork calculations for road and canals,
earthwork in road construction,
how to calculate earthwork excavation quantity,
how to calculate earthwork volume,
calculation of earthwork for road,
Earthwork by Prismoidal Method,
Quantity Survey,
earthwork calculations
Tareef kya karu uski jisne tum he banaya ...
My all time favourite learning chennel
I have no words sir
U r wonderful ❤️❤️❤️🥰🥰😍😍😍😍😍😍
Thanks for appreciation, really means a lot .
Sir please ऐसा numerical भी करा दो जिसमे cutting and filling दोनो हो रही हो।
excellent explanation sir 👍
Thanks for appreciation...Keep supporting.
Also do one video on estimate the quantities of earthworks for canals
ruclips.net/video/EVIa_2OJfJY/видео.html
This video going to help you as this video have Cutting and Filling both ...as we do Earthwork Cutting for canals this video is going to be helpful for you and if u don't understand ..i will make a separate video on Earthwork for Canal
Thankyou so much 4 dis vdo
Anytime ..keep supporting Bro
Thanks sir💚
👍🏻🙏🏻
Sir one example on Trapezoidal rule..!! Plz upload
Thank you for the vid ☺️
Anytime .👍🏻
I think after once learning this ... No one can forget it ...at life time 💯
Means a lot.🙏🏻🙏🏻
What about cutting and filling using this method?
Thank you sir
👍🏻
If intervals not given , what should we do sir
If you are doing Earthwork of a road then these intervals you have to take, otherwise you calculating Cross Section Area, intervals define the length which gives us Quantity
@@CivilConstruction we should assume them ? I have a doubt , how to contact you sir
It usually taken 20,25 or 30 ..but if your Cross Section changing at short interval then you can take intermediate intervals also
@@CivilConstruction how to assume depths , depths also not given
When you know the Ground Level by doing Levelling at site, then as per the grade of the road you have to mark depth of Cutting and Filling at each interval
Prismoidal and Simpson rule methods are same??
Its same
Sir triangle ke base ke jagah sd kaise hua hai
Please reply
S is the slope of the triangle and d is the height. When base is not given, we get base by multiplying given slope(s) by height (d). As slope is given 2:1 which means 2Horizontal distance as in 1 vertical distance. So when 1 m depth is given so that means we need to have 2 m horizontal distance for base if we go by slope. In same way we get base by directly multiplying base with slope
@@CivilConstruction Sir jab 2:1 diya hai to kya ham 2 ko base man sakte hain aur 1 ko height?
Aur kya ye formula hota hai ki base nikalne ke liye slope(s) ko height (d) se multiply karna padta hai ?
Aur 2:1 kis chiz ka ratio rahta hai slope:height ya fir horizontal:vertical ka?
Slope given i.e (s) multiply by by given depth/height (d). 2:1 designates Horizontal: Vertical . e.g if slope ration will be 1.5:1 then we have to take s =1.5 and multiply by depth in order to get the base
@@CivilConstruction Sir 3:5 ratio lekar bata sakte hain kya please
And thank you So much Sir
In that case slope becomes 3÷ 5 =0.6 then multiply it with given depth
Sir I have a doubt
Is prismoidal rule and trapezoidal rule are same...?
By the way good explanation sir😊
Both are different ...Trapezoidal method is known as Average End Area Method
@@CivilConstruction tq sir...
Anytime
Only after a minute did I realize he was alternating languages...
😁😁
Put the notes on drive give link of the notes