Planning and Operational variances - Variance analysis - ACCA Performance Management (PM)

Поделиться
HTML-код
  • Опубликовано: 15 янв 2025

Комментарии • 7

  • @ashanrashmindra5859
    @ashanrashmindra5859 5 лет назад +11

    Good lectures.. I passed MA of CA mainly because of these lectures.. A good teacher

  • @faithcheelo4670
    @faithcheelo4670 5 лет назад +4

    Your lectures are very clear. Thanks

  • @blackm9063
    @blackm9063 2 года назад +1

    Thanks

  • @FULLMOON322
    @FULLMOON322 2 года назад +1

    I am a bit confused why you got 27225 F instead of an Adverse

  • @KevinGomeskvz1990
    @KevinGomeskvz1990 2 года назад

    While calculating the MATERIAL USAGE Planing & operational variance Why did we Use Std Cost of $5 instead of $4.85( revised)?? Shouldn't the Std cost change to $4.85 cuz its revised & updated ????

    • @opentuition
      @opentuition  2 года назад

      There are two ways of calculating planning and operational variance which give different answers (although both ways are accepted in the exam). The way you describe is the way that the previous examiner preferred. However the current examiner prefers the way I do it in my lectures (which is also easier and quicker).
      If you have any more questions please do ask in the free Ask the Tutor Forum on our website. The reason is that I cannot always monitor posts here, but I always answer questions in our Ask the Tutor Forum well within 24 hours.