  • 250.97 Bonding, Metal Raceways - www.MikeHolt.c.... If you remember that the whole purpose of bonding is to establish an “effective ground-fault current path” in order to clear a fault, then you can better understand why proper bonding of raceways is crucial in maintaining a safe electrical installation.
    This video is extracted from Mike Holt's 2020 Bonding and Grounding Textbook and DVD program, for more information visit www.MikeHolt.c... or call 888.632.2633.
    For over 40 years, Mike Holt Enterprises has been providing quality electrical code training to help electrical professionals learn the code, prepare for exams, and improve their electrical knowledge. Visit www.MikeHolt.com for exam preparation tips and training, instructor and curriculum support, continuing education options, free videos and graphics, and so much more.

Комментарии • 24

  • @9111logic
    @9111logic 20 дней назад

    Thank you for this one more clarification 🙏

  • @michaelc.3812
    @michaelc.3812 3 года назад +2

    Mike, you are a great teacher and a very good man. Don’t stop the great work!

    • @MikeHoltNEC
      @MikeHoltNEC  3 года назад +1

      Lol, I'm 'pacing' myself so that I can continue my work for maybe the next ten or fifteen years.

  • @MRELECTRICNY
    @MRELECTRICNY 4 месяца назад +1

    So clearly explained

    • @oculophilia918
      @oculophilia918 3 месяца назад

      Hahahah really?
      Ge cant just say "raising voltage while keeping watts the same decreases the amperage which is a large controbutor to heat and inefficiency."

  • @peikuanfeng3407
    @peikuanfeng3407 3 года назад +1

    The 480/277V system has larger transformer most of the time, such as 2500 kVA. It can deliver higher ground fault current than 120V system. The presentation didn't include transformer impedance. The transformer impedance plays the main role of limiting the fault current magnitude, not the connector resistance. It's not likely the connector resistance can be as high as one ohms.

    • @MikeHoltNEC
      @MikeHoltNEC  3 года назад +3

      The one ohm was an 'example' to see the difference in fault current and heat (squared).

  • @MrEg6hatch
    @MrEg6hatch 2 года назад +3

    Do we need grounding bushing for solar dc circuits at 30a?

  • @0786RICARDO
    @0786RICARDO 5 месяцев назад

    I'm confused about a 250.92 (B)(2), for 2020, they use the word listed threaded hubs. My question is, is it listed for use in the enclosure, or listed for bonding and grounding?
    There's an addition in 2023, threaded entries. Is it factory made? Field attached?
    I also noticed, 2017, It doesn't use the listed terminology for the "threaded hubs". Might they be referring to Myers hubs in 2020?

    • @MikeHoltNEC
      @MikeHoltNEC  5 месяцев назад

      If the hub is listed and installed per the listing instructions, then it meets the requirement of 250.92(B)(2). Which could be a Myers hub.

    • @0786RICARDO
      @0786RICARDO 5 месяцев назад +1

      @@MikeHoltNEC Thank you. Really appreciate all the contributions your enterprise does for us electricians.

  • @relaxtrankis3084
    @relaxtrankis3084 2 года назад +1

    If im doing a Transformer 480/277 on the line side with flex and i punched my own hole do I need a grounding bushing ? I remember you saying in a Video that is just a practice the electricians have but you don't need too but i cant find the video now

    • @MikeHoltNEC
      @MikeHoltNEC  2 года назад +3

      Bonding is required by 250.97. Please review that rule and let us know what you think the answer is. Hint: Bonding is not required...

  • @MM-vr6fj
    @MM-vr6fj 5 месяцев назад

    I have a large metal wireway, for high voltage conductors, which has a sharp edge at the opening inside the cabinet. A smooth rounded aluminum edge guard to protect the cables is being stalled. Does code require this edge guard to be grounded?

    • @MikeHoltNEC
      @MikeHoltNEC  5 месяцев назад

      Please post your question on MikeHolt.Ai.

  • @funstuff9153
    @funstuff9153 3 года назад

    This is only if you don’t have a EGC ran in the pipe with the 277/480. Correct?

    • @illestofdemall13
      @illestofdemall13 3 года назад +3

      No. Still needs to be bonded with a bonding bushing. The point is to create good connection between the 2 metal parts and as the graphic shows, the ringed knockouts aren't sufficient for 277/480VAC. Having a green ground wire inside the conduit isn't going to make that knockout handle a fault better. The metal parts need to be bonded together properly, regardless.

    • @randypierce5887
      @randypierce5887 3 года назад

      Bonding requirements of systems operating at over 150 volts to ground has been in previous code editions . Precautions must be taken with factory stamped concentric & eccentric conduit entries when relying on connection to provide for required metallic raceway bonding or equipment grounding path of ground faults to trip the OCPD.

  • @kevinmccauley3877
    @kevinmccauley3877 2 года назад

    wow you just converted a dinosaur !! LoL, good stuff.

    • @MikeHoltNEC
      @MikeHoltNEC  2 года назад

      No way!

    • @kevinmccauley3877
      @kevinmccauley3877 2 года назад

      @@MikeHoltNEC yes way, and it did not even hurt to accept it.

    • @MikeHoltNEC
      @MikeHoltNEC  2 года назад

      @@kevinmccauley3877 Then you were never a Dinosaur...

    • @kevinmccauley3877
      @kevinmccauley3877 2 года назад

      @@MikeHoltNEC nice TY! one more question, was watching your video multipoint grounding systems but in that you mentioned another video on troubleshooting but i can not find it.

    • @MikeHoltNEC
      @MikeHoltNEC  2 года назад

      @@kevinmccauley3877 I think it's located at MikeHolt.com/NEV