Slow progress on Hinjawadi-Balewadi section in last one month, mainly on entry-exit, station internal work and roof structure. The entire viaduct in this section is complete but station and track work is in progress. Overall in this section, Roof work started 7/12 (+3) Entry-exit work at advanced stage 7/12 (+2) . Please refer chapters in the video description for more updates.
Slow progress on Hinjawadi-Balewadi section in last one month, mainly on entry-exit, station internal work and roof structure. The entire viaduct in this section is complete but station and track work is in progress.
Overall in this section,
Roof work started 7/12 (+3)
Entry-exit work at advanced stage 7/12 (+2) .
Please refer chapters in the video description for more updates.