Pune Metro Line3 Part1 Balewadi to Hinjawadi update | 2-Feb-25

Поделиться
HTML-код
  • Опубликовано: 1 фев 2025

Комментарии •

  • @Metro_vid
    @Metro_vid  3 часа назад +2

    Slow progress on Hinjawadi-Balewadi section in last one month, mainly on entry-exit, station internal work and roof structure. The entire viaduct in this section is complete but station and track work is in progress.
    Overall in this section,
    Roof work started 7/12 (+3)
    Entry-exit work at advanced stage 7/12 (+2) .
    Please refer chapters in the video description for more updates.

  • @yvnlakshmi7855
    @yvnlakshmi7855 2 часа назад +2

    We want metro train from hadaspar to Hinjawadi

  • @darshanvaidya2951
    @darshanvaidya2951 Час назад

    No entry/exit points for stations so far.. dont think it will start this year.

  • @rahulp7313
    @rahulp7313 Час назад

    Slow hai delhi abhi door hai